A Probabilistic-Based Method to Determine Optimum Size of Project Buffer in Construction Schedules
- 1 October 2016
- journal article
- research article
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 142 (10)
Abstract
Buffers are used to deal with the detrimental impacts of uncertainty on projects. However, methods for the allocation of buffers often provide single unique solutions, which are inefficient in the multiobjective decision-making environment of construction. This paper discusses a probabilistic-based buffer allocation method (PBAL), which enables the final decision on buffer size to be made by the project planners based on their preferences about project completion time. It investigates the construction projects where each activity starts as early as possible. Accordingly, the decision involves determining the size of time buffer at the end of the project network. The accuracy of the results is subjected to approximation and numerical errors in the mathematical models among others. Most buffer allocation heuristics for projects have approximation errors and simulation-based techniques introduce numerical errors by their iterative sampling calculation approach. PBAL can minimize these errors by supporting important details of modeling the production in activities, and preserving these details when modeling at the project level. The PBAL capability to minimize mathematical modeling errors and its accuracy has been successfully tested using the records from ten construction projects.Keywords
This publication has 28 references indexed in Scilit:
- Quality Quandaries: Reducing Work in Process at an Emergency Assistance CenterQuality Engineering, 2012
- Time slack-based techniques for robust project scheduling subject to resource uncertaintyAnnals of Operations Research, 2010
- Buffer size design linked to reliability performance: A simulative studyComputers & Industrial Engineering, 2009
- Methodology for Integrated Risk Management and Proactive Scheduling of Construction ProjectsJournal of Construction Engineering and Management, 2008
- A new approximation algorithm for obtaining the probability distribution function for project completion timeComputers & Mathematics with Applications, 2007
- An investigation of buffer sizing techniques in critical chain schedulingEuropean Journal of Operational Research, 2006
- Statistical Methods for Eliciting Probability DistributionsJournal of the American Statistical Association, 2005
- On computing the distribution function of the sum of independent random variablesComputers & Operations Research, 2001
- A Multivariate Approach to Estimating the Completion Time for PERT NetworksJournal of the Operational Research Society, 1986
- Approximating the distribution functions in stochastic networksComputers & Operations Research, 1985