Abstract
Design-build (DB) is an alternative project delivery system that is distinguished by a DB team acting as the single point of responsibility for a project in which the design and construction phases overlap. There are two main methods used to procure DB services: single-step and two-step procurement. Single-step DB involves a request for proposal (RFP) phase, whereas two-step DB involves both request for qualifications (RFQ) and RFP phases. There is an industry perception that more resources are spent to procure single-step DB projects as compared with two-step DB projects. Therefore, this paper focuses on quantifying the resource expenditures and efficiency impacts of single-step and two-step DB through investigating several procurement and project performance metrics. The paper presents results stemming from 32 completed projects. The results of the analysis show that the total cost to industry to develop single-step proposals is approximately 5% of the total project cost, whereas the cost to dev...