Prediction of schedule performance of Indian construction projects using an artificial neural network
- 1 September 2011
- journal article
- research article
- Published by Taylor & Francis in Construction Management and Economics
- Vol. 29 (9) , 901-911
Abstract
Approximately 42% of Indian government-funded construction projects are facing time overruns. With a number of challenging projects around the corner, there is a definite need to overcome these delays. In an earlier study conducted by one of the authors, 55 project performance attributes were identified based on expert opinions and literature surveys, which were subsequently reduced to 20 factors (11 success and nine failure factors) using factor analysis. A second-stage questionnaire survey based on these factors was used to identify the significant schedule performance factors. The analysis of the survey responses led us to conclude that factors such as: a project manager’s competence; monitoring and feedback by project participants; commitment of all project participants; owner’s competence; interaction between external project participants; and good coordination between project participants significantly affect schedule performance. The survey also provided the basis for the development of a schedule performance prediction model. For this, an artificial neural network (ANN) method was used to construct the model, and the best was determined to be a 6-3-1 feed-forward neural network based on a back-propagation algorithm with a mean absolute percentage deviation (MAPD) of 11%. This enables project team members to understand the factors they must monitor closely in order to complete the projects on schedule and to predict performance throughout the course of the project.Keywords
This publication has 21 references indexed in Scilit:
- Critical managerial factors affecting defense projects success: A comparison between neural network and regression analysisEngineering Applications of Artificial Intelligence, 2006
- Predicting project performance through neural networksInternational Journal of Project Management, 2006
- Factors affecting cost performance: evidence from Indian construction projectsInternational Journal of Project Management, 2005
- Design and Build Project Success Factors: Multivariate AnalysisJournal of Construction Engineering and Management, 2001
- Project management: cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteriaInternational Journal of Project Management, 1999
- Critical Success Factors for Different Project ObjectivesJournal of Construction Engineering and Management, 1999
- Neural networks for construction project successExpert Systems with Applications, 1997
- Back-propagation neural networks for modeling complex systemsArtificial Intelligence in Engineering, 1995
- Some Implementations of the BoxplotThe American Statistician, 1989
- Measurement of project successInternational Journal of Project Management, 1988