A Risk-Informed Digital Twin Framework for Sustainable Construction Scheduling and Carbon Optimization Under Uncertainty
Open Access
- 26 July 2026
- journal article
- research article
- Published by MDPI AG in Sustainability
- Vol. 18 (15) , 7599
Abstract
The construction sector accounts for 34% of global energy-related CO2 emissions, yet existing Digital Twin (DT) applications in construction remain largely descriptive, lacking the predictive and prescriptive capabilities required for proactive execution management. This study presents and evaluates, as a simulation-based proof of concept, a risk-informed DT framework integrating a formalized DT state transition model, a dual deep learning prediction engine (Long Short-Term Memory (LSTM) and Transformer), Monte Carlo-based probabilistic carbon quantification for lifecycle modules A1–A5 (S = 10,000), and a risk-adjusted, Non-dominated Sorting Genetic Algorithm II (NSGA-II) optimizer incorporating carbon variance, within a closed weekly feedback loop. The framework is evaluated across five European case studies (residential, education, and commercial office; the Netherlands, the UK, and France) anchored to published project data, with primary calibration on a hybrid real–synthetic mid-rise residential building (CS1; 7200 m2, eight stories, the Netherlands) and a fully documented synthetic layer generating the execution records that the published sources do not provide. Under common random number simulation with 50 execution realizations per case, the full framework achieved simultaneous improvements of 5.8–13.2% in expected schedule duration and 10.4–16.4% in expected embodied carbon relative to a static Critical Path Method (CPM) baseline; for CS1, mean intensity fell from 476 to 426 kgCO2e/m2. Component ablation identified the bi-objective optimizer as the dominant contributor, producing an 11.7–20.2% carbon increase when removed, and the selected Pareto solution was invariant to the risk-aversion parameter λ over [0, 1], indicating that risk adjustment functions as a conservatism margin on the reported carbon target rather than a decision-altering preference. The framework advances construction DTs from descriptive monitoring tools toward risk-informed decision support, offering a transparent and reproducible benchmark that advances data-driven sustainability in construction scheduling and embodied carbon management.Keywords
This publication has 22 references indexed in Scilit:
- AI-Driven Optimization of Scheduling, Risk, and Sustainability in BIM-Enabled Construction Project ManagementArabian Journal for Science and Engineering, 2026
- Uncertainty analysis framework for carbon emissions in building materialization phase using an improved statistical–data quality indicator hybrid methodEnergy and Buildings, 2025
- A Harmonized Dataset of High-Resolution Embodied Life Cycle Assessment Results for Buildings in North AmericaScientific Data, 2025
- Multi objective optimization and evaluation approach of prefabricated component combination solutions using NSGA-II and simulated annealing optimized projection pursuit methodScientific Reports, 2024
- Optimizing construction time, cost, and quality: a hybrid AHP-NSGA-II optimization modelAsian Journal of Civil Engineering, 2024
- A BIM-data mining integrated digital twin framework for advanced project managementAutomation in Construction, 2021
- Developing a dataset of real projects for portfolio, program and project control management researchData in Brief, 2021
- Digital Twin-driven smart manufacturing: Connotation, reference model, applications and research issuesRobotics and Computer-Integrated Manufacturing, 2020
- Machine Learning Algorithms for Construction Projects Delay Risk PredictionJournal of Construction Engineering and Management, 2020
- The ecoinvent database version 3 (part I): overview and methodologyThe International Journal of Life Cycle Assessment, 2016