Shovel Ready Projects and Commercial Construction Activity’s Long and Variable Lags
Open Access
- 1 June 2025
- journal article
- Published by Board of Governors of the Federal Reserve System in Finance and Economics Discussion Series
- p. 1-55
Abstract
We use microdata on the phases of commercial construction projects to document three facts regarding the sector's time-to-plan lags: (1) plan times are long and highly variable, (2) nearly half of projects in planning are abandoned, and (3) property price appreciation reduces the likelihood of abandonment. We write down a tractable model of endogenous planning starts and abandonment that can match these facts. The model also has the testable implication that supply is more elastic when there are more "shovel ready" projects ready for construction. We use local projections to validate this prediction in the cross-section for US cities.Keywords
This publication has 36 references indexed in Scilit:
- Intersectional Complexity in Stereotype ContentAmerican Journal of Sociology, 2023
- Time to build and the real-options channel of residential investmentJournal of Financial Economics, 2020
- Tarnishing the golden and empire states: Land-use restrictions and the U.S. economic slowdownJournal of Monetary Economics, 2018
- Time-to-plan lags for commercial construction projectsRegional Science and Urban Economics, 2016
- Land use regulations and the value of land and housing: An intra-metropolitan analysisJournal of Urban Economics, 2014
- Government investment and fiscal stimulusJournal of Monetary Economics, 2010
- Housing supply and housing bubblesJournal of Urban Economics, 2008
- Urban growth and housing supplyJournal of Economic Geography, 2005
- Land use regulation and new constructionRegional Science and Urban Economics, 2000
- Time to build, option value, and investment decisionsJournal of Financial Economics, 1987