A Duration Prediction Using a Material-Based Progress Management Methodology for Construction Operation Plans
Open Access
- 18 April 2017
- journal article
- research article
- Published by MDPI AG in Sustainability
- Vol. 9 (4) , 635
Abstract
Precise and accurate prediction models for duration and cost enable contractors to improve their decision making for effective resource management in terms of sustainability in construction. Previous studies have been limited to cost-based estimations, but this study focuses on a material-based progress management method. Cost-based estimations typically used in construction, such as the earned value method, rely on comparing the planned budget with the actual cost. However, accurately planning budgets requires analysis of many factors, such as the financial status of the sectors involved. Furthermore, there is a higher possibility of changes in the budget than in the total amount of material used during construction, which is deduced from the quantity take-off from drawings and specifications. Accordingly, this study proposes a material-based progress management methodology, which was developed using different predictive analysis models (regression, neural network, and auto-regressive moving average) as well as datasets on material and labor, which can be extracted from daily work reports from contractors. A case study on actual datasets was conducted, and the results show that the proposed methodology can be efficiently used for progress management in construction.Keywords
Funding Information
- National Research Foundation of Korea, Minisstry of Education (NRF-2015R1D1A1A01058221)
This publication has 25 references indexed in Scilit:
- Automated progress tracking using 4D schedule and 3D sensing technologiesAutomation in Construction, 2012
- Simulation model incorporating genetic algorithms for optimal temporary hoist planning in high-rise building constructionAutomation in Construction, 2011
- A CBR-based hybrid model for predicting a construction duration and cost based on project characteristics in multi-family housing projectsCanadian Journal of Civil Engineering, 2010
- Management and analysis of unstructured construction data typesAdvanced Engineering Informatics, 2008
- Assessing research issues in Automated Project Performance Control (APPC)Automation in Construction, 2007
- A formalism for utilization of sensor systems and integrated project models for active construction quality controlAutomation in Construction, 2006
- Comparison of construction cost estimating models based on regression analysis, neural networks, and case-based reasoningBuilding and Environment, 2004
- Hybrid fuzzy least-squares regression analysis and its reliability measuresFuzzy Sets and Systems, 2001
- BAYESIAN REGRESSION ANALYSIS WITH SCALE MIXTURES OF NORMALSEconometric Theory, 2000
- Forecasting residential construction demand in Singapore: a comparative study of the accuracy of time series, regression and artificial neural network techniquesEngineering, Construction and Architectural Management, 1998