Abstract
During the mining works on the construction of the new production shaft of the Čukaru Peki mine in Bor, waste are excavated. This waste are temporarily deposited at the landfill in the immediate vicinity of the new production shaft. From the landfill, waste are loaded and transported to the waste dump where they are permanently disposed of. The construction of the landfill and waste dump site was carried out in the Gems software, in which a 3D model of these objects was constructed. Quantities were calculated in the Minex software.