Integrated Parametric Graph Closure and Branch-and-Cut Algorithm for Open Pit Mine Scheduling under Uncertainty
Open Access
Abstract
Open pit mine production scheduling is a computationally expensive large-scale mixed-integer linear programming problem. This research develops a computationally efficient algorithm to solve open pit production scheduling problems under uncertain geological parameters. The proposed solution approach for production scheduling is a two-stage process. The stochastic production scheduling problem is iteratively solved in the first stage after relaxing resource constraints using a parametric graph closure algorithm. Finally, the branch-and-cut algorithm is applied to respect the resource constraints, which might be violated during the first stage of the algorithm. Six small-scale production scheduling problems from iron and copper mines were used to validate the proposed stochastic production scheduling model. The results demonstrated that the proposed method could significantly improve the computational time with a reasonable optimality gap (the maximum gap is 4%). In addition, the proposed stochastic method is tested using industrial-scale copper data and compared with its deterministic model. The results show that the net present value for the stochastic model improved by 6% compared to the deterministic model.Keywords
Funding Information
- Council of Scientific and Industrial Research, India (22 (0595)/12/EMR – II)
This publication has 33 references indexed in Scilit:
- Pit optimisation and life of mine scheduling for a tenement in the Central African CopperbeltInternational Journal of Mining, Reclamation and Environment, 2013
- A diversified Tabu search approach for the open-pit mine production scheduling problem with metal uncertaintyEuropean Journal of Operational Research, 2012
- Multivariate Block-Support Simulation of the Yandi Iron Ore Deposit, Western AustraliaMathematical Geosciences, 2012
- Production scheduling with uncertain supply: a new solution to the open pit mining problemOptimization and Engineering, 2012
- Block size selection with the objective of minimizing the discrepancy in real and estimated block gradeArabian Journal of Geosciences, 2011
- Flexible open-pit mine design under uncertaintyJournal of Mining Science, 2011
- Stochastic optimization for strategic mine planning: A decade of developmentsJournal of Mining Science, 2011
- Long-term open pit mine production planning: a review of models and algorithmsInternational Journal of Mining, Reclamation and Environment, 2008
- A maximum upside / minimum downside approach to the traditional optimization of open pit mine designJournal of Mining Science, 2007
- Traditional and New MIP Models for Production Scheduling With In-Situ Grade VariabilityInternational Journal of Surface Mining, Reclamation and Environment, 2004