Neutrosophic fuzzy-based graphical evaluation and review technique for construction scheduling for residential buildings
- 21 April 2025
- journal article
- Published by SAGE Publications in Intelligent Decision Technologies
- Vol. 19 (4) , 2267-2294
Abstract
This study introduces Neutrosophic Fuzzy GERT (NF-GERT) as a robust approach for scheduling complex construction projects, addressing limitations in conventional methodologies (PERT, CPM, PDM). NF-GERT leverages Graphical Evaluation and Review Technique (GERT) for stochastic project network analysis and Neutrosophic Fuzzy Sets (NFS) to handle uncertainty in activity durations. Specifically, a single-valued trapezoidal NFS captures Truth (T), Indeterminacy (I), and Falsity (F) subsets, providing a nuanced representation of ambiguity. The integrated multimethodology, NF-GERT, proves effective in managing uncertainties, demonstrated through a fourteen-storey residential case study, and validated with comparisons across forty-five real-time projects of varying complexities. The results highlight the effectiveness of the NF-GERT methodology in managing uncertainty and indeterminacy, further supported by statistical analysis using ANOVA. Acknowledging subjectivity, the study emphasizes clear guidelines, iterative refinement, and Monte Carlo analysis for consensus and reliability. NF-GERT emerges as a promising approach for realistic and reliable scheduling of construction projects amidst uncertainties and complexities.Keywords
This publication has 94 references indexed in Scilit:
- Optimizing system reliability through selective maintenance allocation: A novel multi‐objective programming approach using neutrosophic fuzzy conceptQuality and Reliability Engineering International, 2023
- Stochastic Project Network Scheduling Technique for Construction Projects Using GERT2022
- Analyzing Shortest Path Problem via Single-Valued Triangular Neutrosophic Numbers: A Case Study2021
- Numerical Modeling of Business Processes Using the Apparatus of GERT Networks2021
- Neutrosophic Operational Research2021
- Stochastic Scheduling of Production Orders Under Uncertainty2017
- An Estimating Method for IT Project Expected Duration Oriented to GERT2007
- Fuzzy Set Theory—and Its Applications2001
- Planning under Precedence/Duration Constraints: Networking Techniques1990
- Fuzzy logic and approximate reasoningSynthese, 1975