Assembly Technology for the W7-X Stellarator
Author:
- 1 September 2005
- conference paper
- Published by Institute of Electrical and Electronics Engineers (IEEE)
- p. 1-4
Abstract
Wendelstein 7-X is a superconducting Sellarator being constructed in Greifswald, Germany. The technology needed to assemble the basic-machine W7-X requires a complex integration of engineering disciplines from the accuracy of manufacture through to the metrology techniques and equipment to successfully assemble the machine. The spiral shape of the Stellarator vacuum vessel means the 70 coils must be threaded individually over the vacuum vessel. To avoid damage to the thermal insulation 5 axis lifting devices have been designed to thread coils into their final position. The distance between the coils is fixed by a series of radial and lateral support elements, central support elements and planar support elements, the assembly technology is being developed and tested by an extensive test programme. W7-X is equipped with 299 ports for diagnostics and supply of in vessel components; they connect the ICRH, ECRH and neutral injection systems to the plasma vessel. All ports must be positioned accurately at various angles around the vacuum vessel, ranging in weight from 100 kg up to 900 kg. For the ports this requires close integration of the manufacturing, metrology and assembly technologies. At present it is planned to use a powered ramp. It is planned that the ramp and its support structure will also be used to insert the thermal insulation of the port, the 'plug in' in vessel component supply bundles and possibly diagnostics. The bus bar system links all coils to the power supply system. Space constraints within the machine cryostat require compact superconducting joints which, have been designed and tested with a resistance in the range of lnOhm. The paper will give an overview of the various technologies being used to solve the assembly problems on the various components and the status of the assembly of the basic-machineKeywords
This publication has 8 references indexed in Scilit:
- WENDELSTEIN 7-X at the transition to assemblyFusion Engineering and Design, 2005
- Manufacture of the vacuum vessels and the ports of Wendelstein 7-XFusion Engineering and Design, 2005
- Strategy of Structural Analysis of W7-X Magnet System2005
- Design and test of the support elements of the W7-X magnet system2005
- Preload Experiments on Wendelstein 7X Attachment System of the Superconducting Coils2005
- Wendelstein 7-X, Overview and Status of Construction2005
- Design of Narrow Support Elements for Non Planar Coils of Wendelstein 7-X2005
- Design and Construction of the Superconducting Bussystem for the Stellarator W7-X2005