Client and contractor roles in schedule incentive/disincentive projects
- 11 February 2019
- journal article
- research article
- Published by Emerald Publishing in Engineering, Construction and Architectural Management
- Vol. 26 (3) , 386-407
Abstract
Purpose: Delays in construction projects can be very expensive due to their adverse effects on project cost and profit margin. To overcome this problem, clients in the construction industry sometimes use schedule incentive/disincentive (I/D) contracting strategy. However, previous studies have shown that inadequate understanding and wrong implementation of schedule I/D provisions could result in unintended results. Moreover, the use of the I/D contracting method is in its initial stages in many countries such as India. The purpose of this paper is to identify various factors that are essential for schedule I/D success in construction projects. Design/methodology/approach: A questionnaire survey was conducted among experienced professionals (clients, contractors and consultants) from across the Indian construction industry. Findings: Top success factors related to clients in the descending order of their importance are: realistic targets; detailed guidelines for I/D implementation; close coordination with other stakeholders; correct estimation of I/D duration and amount; and imposing disincentives after due consideration. Meanwhile, factors related to contractor organisations are: continuous monitoring and control; thorough understanding of schedule I/D targets; specific considerations in appointing senior project personnel; effective communication; and proper labour management. Research limitations/implications: This empirical research was conducted in the Indian construction industry. Similar studies from developed construction markets may provide more insights into the successful use of schedule I/D provisions in construction projects. Practical implications: The uptake of these recommendations is likely to increase the success of schedule I/D provisions in construction projects, especially in developing countries where the use of I/D contracting strategy is not very popular. Originality/value: This research highlights the specific roles of both clients and contractors in the success of schedule I/D projects in developing countries such as India.Keywords
This publication has 69 references indexed in Scilit:
- Understanding triangulation in researchEvidence-Based Nursing, 2013
- Critical Success Factors for Key Project Players and Objectives: Case Study of SingaporeJournal of Construction Engineering and Management, 2013
- Decision support model for incentives/disincentives time–cost tradeoffAutomation in Construction, 2012
- Procurement Contracting With Time Incentives: Theory and Evidence *The Quarterly Journal of Economics, 2011
- Motivation toward financial incentive goals on construction projectsJournal of Business Research, 2011
- Determination of Contract Time and Incentive and Disincentive Values of Highway Construction ProjectsInternational Journal of Construction Education and Research, 2010
- Client recommendations for financial incentives on construction projectsEngineering, Construction and Architectural Management, 2010
- Issues in using methodological triangulation in researchNurse Researcher, 2009
- Analysis of craft workers' and foremen's perceptions of the factors affecting construction labour productivityConstruction Management and Economics, 2007
- The significant factors causing delay of building construction projects in MalaysiaEngineering, Construction and Architectural Management, 2007