A finite element model for pre‐stressed or post‐tensioned concrete wind turbine towers
Authors:
- 3 July 2014
- journal article
- research article
- Published by Wiley in Wind Energy
- Vol. 18 (9) , 1593-1610
Abstract
Wind turbine support towers have been traditionally formed of structural steel tubular sections, being fabricated in large sections under factory conditions before being transported to site for erection. Given the trend towards developing turbines with hub heights in excess of 90 m, it is now necessary to develop towers of concrete and other materials that can provide improved dynamic properties and ease transportation difficulties over the structural steel solutions. Concrete towers of this height require pre‐stressing to overcome high vertical stresses induced in bending, which would otherwise lead to cracking in the concrete, with a resulting reduction in the tower's natural frequency. In order to properly understand the behaviour of concrete towers, it is necessary to take account of both material and geometric non‐linearity. Material non‐linearity of concrete is well understood, and geometric non‐linearity arises because of the imposition of an initial stress into the concrete by way of the application of pre‐stress. In this paper, a finite element model is proposed, which will describe the concrete as a continuum of four‐noded, two‐dimensional Reisser–Mindlin shell elements. The pre‐stressing tendons are to be represented by one‐dimensional bar elements, with an imposed pre‐stress. For the numerical examples considered in the paper, tendons are modelled to be post‐tensioned and debonded. The effect of varying the design parameter of magnitude of pre‐stress and the time dependence of pre‐stress force has been investigated using the model described. The impact that concrete compressive strength had on overall tower stiffness was also investigated. Copyright © 2014 John Wiley & Sons, Ltd.Keywords
This publication has 12 references indexed in Scilit:
- Nonlinear Finite-Element Analysis of Posttensioned Concrete Bridge GirdersJournal of Bridge Engineering, 2011
- Natural frequencies of bonded and unbonded prestressed beams–prestress force effectsJournal of Sound and Vibration, 2006
- Time domain responses of a prestressed beam and prestress identificationJournal of Sound and Vibration, 2005
- LWST Phase I Project Conceptual Design Study: Evaluation of Design and Construction Approaches for Economical Hybrid Steel/Concrete Wind Turbine Towers; June 28, 2002 -- July 31, 20042005
- Analysis and design of the prototype of a steel 1-MW wind turbine towerEngineering Structures, 2003
- Static, seismic and stability analyses of a prototype wind turbine steel towerEngineering Structures, 2002
- A theoretical study of force identification using prestressed concrete bridgesEngineering Structures, 2000
- Dynamic Characteristics of Post-Tensioned Girders with Web OpeningsJournal of Structural Engineering, 1996
- Prestress Force Effect on Vibration Frequency of Concrete BridgesJournal of Structural Engineering, 1994
- On the dynamic response of a prestressed beamJournal of Sound and Vibration, 1976