An Improved Spatial Scheduling Algorithm for Block Assembly Shop in Shipbuilding Company
Authors:
- Shiegheun KohSKShiegheun Koh
- Chanho EomCEChanho Eom
- Junghee JangJJJunghee Jang
- Yongsun ChoiYCYongsun Choi
- 1 January 2008
- conference paper
- Published by Institute of Electrical and Electronics Engineers (IEEE)
- p. 253
Abstract
Motivated by a software development project in a shipbuilding company, we propose a production scheduling algorithm for the block assembly shop in a shipbuilding company. The problem is very complicated and time consuming because it should consider both scheduling and spatial arrangement of each block simultaneously. To reflect the scheduling dynamics, we propose an improved schedule policy, named the LCA (largest contact area) policy. Using real shipyard data, we showed that the block assembly scheduling system based on the policy made a good performance.Keywords
This publication has 4 references indexed in Scilit:
- A spatial scheduling application at the block paint shop in shipbuilding: the HYPOS projectProduction Planning & Control, 2002
- Modeling and solving the spatial block scheduling problem in a shipbuilding companyComputers & Industrial Engineering, 1996
- A spatial scheduling system and its application to shipbuilding: DAS-CURVEExpert Systems with Applications, 1996
- Spatial Planning: A Configuration Space ApproachIEEE Transactions on Computers, 1983