Using discounted cash flow heuristics to improve project net present valve
Authors:
- 1 September 1996
- journal article
- Published by Wiley in Journal of Operations Management
- Vol. 14 (3) , 229-240
Abstract
The problem of scheduling resource‐constrained projects to maximize their Net Present Value (NPV) is studied in this paper. The performance of seventeen scheduling heuristics, ten of which are original to this work, is evaluated. Heuristic performance is rated separately on maximization of project NPV and minimization of project duration. Two of the new heuristics are significantly better than the standard heuristics at yielding higher project NPVs. These two heuristics also perform well at reducing project duration. Two heuristics, Minslack and Shortest Processing Time (SPT), that performed well in previous studies are shown to be poor performers at maximizing project NPV.Keywords
This publication has 18 references indexed in Scilit:
- A tabu search procedure for the resource constrained project scheduling problem with discounted cash flowsComputers & Operations Research, 1994
- Early-tardy cost trade-offs in resource constrained projects with cash flows: An optimization-guided heuristic approachEuropean Journal of Operational Research, 1993
- The scheduling of activities to maximize the net present value of projectsEuropean Journal of Operational Research, 1990
- A Comparison of Due Date Setting, Resource Assignment, and Job Preemption Heuristics for the Multiproject Scheduling Problem*Decision Sciences, 1990
- Towards the standardization of performance measures for project scheduling heuristicsIEEE Transactions on Engineering Management, 1988
- Multi-Project Scheduling: Categorization of Heuristic Rules PerformanceManagement Science, 1982
- Scheduling a Project to Maximize Its Present Value: A Zero-One Programming ApproachManagement Science, 1977
- Project Network Summary Measures Constrained- Resource SchedulingA I I E Transactions, 1975
- A Comparison of Heuristic and Optimum Solutions in Resource-Constrained Project SchedulingManagement Science, 1975
- The payment scheduling problemNaval Research Logistics Quarterly, 1972