Fabrication of an ITER Shielding Blanket Prototype
Authors:
- 1 November 1998
- journal article
- research article
- Published by American Nuclear Society in Fusion Technology
- Vol. 34 (3P2) , 892-898
Abstract
A full-scale prototype mockup of the ITER shielding blanket composed of the first wall with built-in circular tubes and the shield block has been successfully fabricated. Joints of the first wall/the shield block as well as those of the DSCu/DSCu, DSCu/SS and SS/SS in the first wall, were simultaneously HIP bonded. The fabricated prototype mockup fully satisfied the specified design conditions such as dimensional accuracy, pressure-resistance, etc. After HIPping, HIPped interfaces were metallographically observed with pieces cut from the edge of the mockup. There were no harmful voids at the bonded interfaces, and good bondability of simultaneous HIP method was confirmed. In addition, engineering data on fabrication including bonding deformation were obtained.Keywords
This publication has 3 references indexed in Scilit:
- Mechanical properties of HIP bonded joints of austenitic stainless steel and Cu-alloy for fusion experimental reactor blanketJournal of Nuclear Materials, 1996
- Structural materials for ITER in-vessel component designJournal of Nuclear Materials, 1996
- Development of blanket box structure fabrication technologyFusion Engineering and Design, 1995