Research on Mathematical Model of Cost Budget in the Early Stage of Assembly Construction Project Based on Improved Neural Network Algorithm
Open Access
- 15 July 2020
- journal article
- research article
- Published by Wiley in Mathematical Problems in Engineering
- Vol. 2020, 1-7
Abstract
In view of the poor performance of the original mathematical model of assembly construction project precost budget, a mathematical model of assembly construction project precost budget based on improved neural network algorithm is proposed. This paper investigates the cost content of assembly construction project and analyzes its early cost. It finds that the early cost of assembly construction project includes component production cost, transportation component cost, and installation component cost. Based on the improved neural network algorithm to build an improved neural network model, the improved neural network model to mine the cost data in the early stage of assembly construction project is used. In this paper, the earned value variable is introduced to transform the project duration and project cost in the early stage of the prefabricated construction project into quantifiable cost data, and the earned value analysis method is used to estimate the implementation cost of the prefabricated construction project. According to the result of cost estimation, the mathematical model of precost budget of prefabricated construction project is built based on the project parameters. In order to prove that the cost budget performance of the mathematical model based on the improved neural network algorithm in the early stage of assembly construction project is better, the original mathematical model is compared with the mathematical model, the experimental results show that the cost budget performance of the model is better than the original model, and the cost budget performance is improved.Keywords
Funding Information
- Chongqing Municipal Education Commission (KJQN201904003, ZD2016-04)
- Chongqing Technology and Business Institute (KJQN201904003, ZD2016-04)
This publication has 17 references indexed in Scilit:
- A modified firefly algorithm-artificial neural network expert system for predicting compressive and tensile strength of high-performance concreteConstruction and Building Materials, 2018
- Artificial neural network model for forecasting sub-hourly electricity usage in commercial buildingsEnergy and Buildings, 2016
- Conceptual Cost Estimation Model for Engineering Services in Public Construction ProjectsJournal of Management in Engineering, 2016
- Activity based risk assessment and safety cost estimation for residential building construction projectsSafety Science, 2015
- Cost Estimation of Laser Additive Manufacturing of Stainless SteelPhysics Procedia, 2015
- Cost estimation of building individual cooperative housing with crowdfunding model: case of Beijing, ChinaJournal of Intelligent Manufacturing, 2014
- A fuzzy nearest neighbor neural network statistical model for predicting demand for natural gas and energy cost savings in public buildingsExpert Systems with Applications, 2014
- Mathematical Model for Optimization of Construction Contracting in Housing Development ProjectProcedia - Social and Behavioral Sciences, 2013
- Cost premium prediction of certified green buildings: A neural network approachBuilding and Environment, 2011
- Conceptual cost estimates using evolutionary fuzzy hybrid neural network for projects in construction industryExpert Systems with Applications, 2010