Abstract
A restoration switching action may satisfy static power-flow requirements yet fail frequency or protection constraints. We develop a model-relative joint certificate combining a sign-aware frequency envelope, primary and counterfactual backup clearing deadlines, inverse-time relay coordination and breaker-delay uncertainty. For fixed scalar-scaled piecewise-current traces and stipulated monotone full, hold or linear-reset timers, we prove an exact independent-rectangle endpoint criterion. An analytic counterexample demonstrates that the two endpoints of correlated common-current derating can pass coordination while an interior realization fails. A reproducible synthetic benchmark of 90 cases compares nominal, common-endpoint, rectangular and finite time-domain screens: the respective false approvals against the rectangular model reference are 19, 3, 0 and 0. Controlled ablations identify the coordination margin and frequency gate as major observed contributors to excluding false approvals. Pinned IEEE 123-bus OpenDSS probes provide feeder-model evidence but do not establish energized phase continuity through transformer/regulator windings, installed protection orientation or an authorized restoration sequence; disabling a named switch yields zero reported voltage at two monitored buses despite numerical convergence. The resulting certificates and numerical comparisons are restricted to their stated models and do not constitute electromagnetic-transient or field safety validation.