Measuring the Impact of Scope Changes on Project Plan Using EVM
Open Access
- 20 August 2020
- journal article
- research article
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Access
- Vol. 8, 154589-154613
Abstract
Earned Value Management (EVM) measures project performance against a baseline plan. It identifies deviations in budget and schedule, aids project managers in taking earlier corrective actions against cost and schedule overruns. Although the literature highlights the significance of scope by adopting it as a leading indicator to measure project success or failure. However, EVM does not include scope when evaluating the performance of any software project. While considering the importance of scope and its ever-changing nature, it is imperative to measure the effect of changes in scope on the project plan. To analyse such effects, this study aims to enhance the traditional EVM by incorporating scope into it. The main objectives of this paper are: i) to extract the effects of project scope changes, ii) to map extracted effects of project scope changes with Software Project Scope Rating Index (SPSRI) elements, and iii) to quantify the extracted effects and integrate them with EVM. An extensive literature review is conducted to achieve the first objective, which results in the seventeen unique effects; that were used to map with SPSRI elements. To forecast the variations in scope for a given project budget, Monte Carlo simulations were run on the top eight scope elements, whereas, the results were incorporated with EVM to identify the deviations between actual and projected values of scope’s score and cost. Finally, the multivariate regression model was used to evaluate the influence of individual element on the overall estimated cost of the project. The correlation between the independent variables (SPSRI elements) and the dependent variable (overall cost) was calculated along with the valuation of each independent variable on the dependent variable. Moreover, the effects are statistically shown that independent variables have influenced the dependent variable. This technique could assist the project managers to forecast deviations in project scope earlier.Keywords
Funding Information
- Deanship of Scientific Research (DSR), King Abdulaziz University, Jeddah (D-648-611-1441)
This publication has 66 references indexed in Scilit:
- Monitoring project duration and cost in a construction project by applying statistical quality control chartsInternational Journal of Project Management, 2013
- A time-dependent earned value model for software projectsInternational Journal of Project Management, 2011
- Impact of Software Requirement Volatility Pattern on Project Dynamics: Evidences from a Case StudyInternational Journal of Software Engineering & Applications, 2011
- Measuring the flow in lean software developmentSoftware: Practice and Experience, 2011
- Analyzing the benefits of lean manufacturing and value stream mapping via simulation: A process sector case studyInternational Journal of Production Economics, 2007
- Kerzner's Project Management Logic Puzzles (Kerzner, H.; 2006)IEEE Transactions on Engineering Management, 2007
- Essential elements of questionnaire design and developmentJournal of Clinical Nursing, 2007
- Software project risks and their effect on outcomesCommunications of the ACM, 2004
- Plans are nothing, changing plans is everything: the impact of changes on project successResearch Policy, 2004
- A Case Study on Agile Estimating and Planning using ScrumElektronika ir Elektrotechnika, 1970