A new open-pit mine planning optimization method using block aggregation and integer programming
Authors:
Open Access
- 1 January 2018
- journal article
- research article
- Published by Academy of Science of South Africa in Journal of the Southern African Institute of Mining and Metallurgy
- Vol. 118 (7) , 705-714
Abstract
Mathematical programming has been applied to optimizing open pit mine planning problems since the early 1960s. Nonetheless, it still remains challenging to obtain a life-of-mine plan with current computational hardware and software, mostly because of the scale of the input data, which is generally in the form of mining blocks. To overcome this challenge, one common practice is to aggregate blocks into larger units before formulating and solving mine planning models. However, the majority of available block aggregation techniques ignore the slope relation between blocks or are simply not capable of controlling the number of aggregates generated. In this study, a new optimization method for open pit mine planning is proposed, which consists of two stages. In the first stage, a new block aggregation algorithm is proposed, called the TopCone algorithm (TCA), where blocks are clustered into TopCones (TCs), which have two important features: (1) the cone shape and (2) the number of TCs that can be explicitly controlled. In the second stage, TCs form the basis of an integer programming model with a variety of operational constraints so that a high-quality production scheduling solution can be obtained in relatively quick computational time. The capability and novelty of the proposed method is demonstrated through the optimization of the long-term production schedule of a large-scale copper deposit. The case study shows higher NPV results compared to a commercial software package, and the entire mine planning process can be completed in less than 10 minutes.Keywords
This publication has 13 references indexed in Scilit:
- Aggregation heuristic for the open-pit block scheduling problemEuropean Journal of Operational Research, 2016
- A hybrid method based on linear programming and variable neighborhood descent for scheduling production in open-pit minesJournal of Global Optimization, 2014
- A diversified Tabu search approach for the open-pit mine production scheduling problem with metal uncertaintyEuropean Journal of Operational Research, 2012
- A new MIP model for mine equipment scheduling by minimizing maintenance costEuropean Journal of Operational Research, 2010
- A strengthened formulation and cutting planes for the open pit mine production scheduling problemComputers & Operations Research, 2010
- LP-based disaggregation approaches to solving the open pit mining production scheduling problem with block processing selectivityComputers & Operations Research, 2009
- The new Fundamental Tree Algorithm for production scheduling of open pit minesEuropean Journal of Operational Research, 2007
- An Application of Branch and Cut to Open Pit Mine SchedulingJournal of Global Optimization, 2003
- A fuzzy linear programming model for production planning in coal minesComputers & Operations Research, 1997
- Optimal mine production scheduling: evaluation of large scale mathematical programming approachesGeotechnical and Geological Engineering, 1983