Distribution of the Activity Time in Network Analysis: A Critical Revisit with a Gamma Alternative
Authors:
- 10 January 2013
- journal article
- research article
- Published by Taylor & Francis in Communications in Statistics - Simulation and Computation
- Vol. 42 (6) , 1288-1297
Abstract
Network analysis is an important technique for project management. However, the current literature is biased toward beta distribution for modeling activity times. In this article, we have critically examined the role of beta distribution. It has been shown that beta distribution plays no specific role. Further, the method for calculating the chance of project completion must be revised. We have accordingly suggested an alternative modeling in terms of gamma distribution and proposed how to calculate the chance of project completion by taking into consideration both critical and noncritical paths. For demonstration purposes, we have considered a small project.Keywords
This publication has 12 references indexed in Scilit:
- Evaluating project completion times when activity times are Weibull distributedEuropean Journal of Operational Research, 2004
- A study of approximating the moments of the job completion time in PERT networksJournal of Operations Management, 1996
- Better Estimation of PERT Activity Time ParametersManagement Science, 1993
- Reply—An Answer to Sasieni's Question on PERT TimesManagement Science, 1987
- Note—A Note on Pert TimesManagement Science, 1986
- Stochastic pert networks: OP diagrams, critical paths and the project completion timeComputers & Operations Research, 1985
- Bounding the Project Completion Time Distribution in PERT NetworksOperations Research, 1985
- Three-Point Approximations for Continuous Random VariablesManagement Science, 1983
- Estimating the Mean and Variance of Subjective Distributions in PERT and Decision AnalysisManagement Science, 1975
- An Analytical Study of the PERT AssumptionsOperations Research, 1964