The 2025 El Teniente Andesita collapse: corridor-scale multi-cave coupling and stress-path–driven shear instability
Authors:
- Amin HekmatnejadAHAmin Hekmatnejad
- Mahdi BajolvandMBMahdi Bajolvand
- Parsa AlizadehPAParsa Alizadeh
- Nayadeth CortesNCNayadeth Cortes
Preprint
- 24 February 2026
- preprint
- Published by Elsevier in SSRN Electronic Journal
Abstract
High-consequence instabilities in deep block/panel caving are increasingly linked to multi-cave coupling, yet the controlling mechanism is often described in fragmented terms (excavation interaction, high stress, or fault slip), limiting actionable design and sequencing guidance. Motivated by the 2025 El Teniente (Andesita) corridor, this study tests whether excavation-driven stress-path evolution during multi-cave convergence can shift a district from stable, abutment-dominated loading to an unstable shear-dominated regime, enabling high-magnitude induced seismicity (Mw ~3.8–4.5) and increasing rockburst/collapse potential. We couple (i) continuum stress-transfer modeling of evolving cave footprints and interaction pillars with (ii) progressive failure simulation (FDEM) to resolve stress amplification, σ₁ re-orientation, and EDZ transmission under bounded geometric and stress scenarios. Results show that higher σHmax expands the mechanical footprint of caving by amplifying induced-stress halos and EDZ reach, reducing margins for decoupling between stacked horizons. As plan-view spacing narrows, the system transitions from conditional interaction to near-coalescent, bridge-dominated loading, producing sustained corridor stresses of ~90–130 MPa with local peaks approaching ~170 MPa and amplified displacements. Within this unified stress-path framework, fault reactivation and new shear-rupture localization emerge as competing expressions: where persistent structures are favorably oriented, modeled slip histories support episodic reactivation; where structural slip is unfavorable or absent, damage connectivity and confinement/normal-stiffness degradation promote a staged transition toward through-going shear rupture. Order-of-magnitude seismic scaling indicates that decimeter- to meter-scale slip can correspond to Mw ≈ 3.8–4.8, consistent with Mw ~3.5–4.5-class disturbances in the northern corridor (e.g., 2023 Mw ~3.8; 2025 ~Mw ~4.2). The results provide mechanism-based guidance for interaction-aware spacing, sequencing, undercut ramp-up control, and risk-indexed planning, including localized method adaptation in high-risk structural corridorsKeywords
This publication has 21 references indexed in Scilit:
- Influence of tunnel excavation on the magnitude and rotation angle of principal stress in surrounding rockScientific Reports, 2024
- Rockburst in underground excavations: A review of mechanism, classification, and prediction methodsUnderground Space, 2022
- Discussions on rockburst and dynamic ground support in deep minesJournal of Rock Mechanics and Geotechnical Engineering, 2019
- Pillar Burst Assessment Based on Large-scale Numerical ModelingProcedia Engineering, 2017
- Application of Synthetic Rock Mass modeling to veined core-size samplesInternational Journal of Rock Mechanics and Mining Sciences, 2016
- Slip tendency analysis, fault reactivation potential and induced seismicity in a deep geothermal reservoirJournal of Structural Geology, 2009
- Seismicity Induced by Mining: Recent Research2009
- Stress field analysis at the El Teniente Mine: evidence for N–S compression in the modern AndesJournal of Structural Geology, 2003
- Slip-tendency analysis and fault reactivationGeology, 1996
- A moment magnitude scaleJournal of Geophysical Research, 1979