Understanding and managing iterative error and change cycles in construction
Authors:
- 1 March 2007
- journal article
- research article
- Published by Wiley in System Dynamics Review
- Vol. 23 (1) , 35-60
Abstract
Errors and changes in construction often result in significant schedule and cost overruns affecting project performance. To understand the nature of these errors and changes and to ultimately reduce their detrimental impacts on project performance, this paper presents a system dynamics‐based construction model, which focuses on the dynamics of error and change management in construction, including quality management, scope management, the request for information process, and the decision‐making process for the approval of changes, and their consequent detrimental impacts on project performance. In particular, the developed model integrates several concepts in traditional network‐based tools to enhance the applicability of the model. Describing the dynamic behaviors generated by the developed model and applying the model to a couple of real‐world construction projects, this paper concludes that: (1) realism should be added to schedule planning; (2) an efficient coordination process is needed; (3) proactive contingency plans need to be taken into consideration; and (4) integration of network‐based tools and system dynamics‐based models can contribute to management of errors and changes. Copyright © 2007 John Wiley & Sons, Ltd.Keywords
This publication has 14 references indexed in Scilit:
- Quality and Change Management Model for Large Scale Concurrent Design and Construction ProjectsJournal of Construction Engineering and Management, 2005
- Change Orders Impact on Labor ProductivityJournal of Construction Engineering and Management, 2005
- Dynamic change management for construction: introducing the change cycle into model‐based project managementSystem Dynamics Review, 2003
- Strategic management of complex projects: a case study using system dynamicsSystem Dynamics Review, 2001
- The causes and costs of defects in constructionAutomation in Construction, 1999
- A quantitative study of post contract award design changes in constructionConstruction Management and Economics, 1999
- Optimization of Resource Allocation and Leveling Using Genetic AlgorithmsJournal of Construction Engineering and Management, 1999
- Dynamic modeling of product development processesSystem Dynamics Review, 1998
- Fast-Tracking's Impact on Project ChangeProject Management Journal, 1998
- Naval Ship Production: A Claim Settled and a Framework BuiltInterfaces, 1980