Quantifying the interruption impact of activity delays in non-serial repetitive construction projects
Authors:
- 13 September 2019
- journal article
- research article
- Published by Taylor & Francis in Construction Management and Economics
- Vol. 38 (6) , 515-533
Abstract
Available scheduling models for repetitive construction projects can be classified as serial or non-serial. Serial models assume that each repetitive activity is limited to have only one predecessor and one successor, while non-serial models enable repetitive activities to have multi predecessors and successors. Activity delays in serial and non-serial repetitive projects often cause work interruptions for successor activities and project delays. This paper presents the development of a novel scheduling model for both serial and non-serial repetitive construction projects to quantify the impact of any activity delay on interrupting the crew work continuity of its successors. An application example of a repetitive construction project from the literature is analyzed to illustrate the use of the model and its computations. This analysis illustrates the novel capabilities of the model in: (1) calculating a new float to identify the duration that each activity can be delayed without causing interruption in the crew work continuity of any of its successors; and (2) quantifying the impact of unexpected activity delay on interrupting the crew work continuity of its successors. These capabilities enable construction planners to analyze and minimize the impact of unexpected activity delays on interrupting the crew work continuity of all its successors.Keywords
This publication has 17 references indexed in Scilit:
- Float Types in Linear Schedule Analysis with Singularity FunctionsJournal of Construction Engineering and Management, 2009
- Genetic algorithm-based multi-objective model for scheduling of linear construction projectsAdvances in Engineering Software, 2008
- Problems causing delays in major construction projects in ThailandConstruction Management and Economics, 2008
- Work Continuity Constraints in Project SchedulingJournal of Construction Engineering and Management, 2006
- Optimal Planning and Scheduling for Repetitive Construction ProjectsJournal of Management in Engineering, 2006
- Algorithm for Determining Controlling Path Considering Resource ContinuityJournal of Computing in Civil Engineering, 2001
- Linear Scheduling Model: Float CharacteristicsJournal of Construction Engineering and Management, 2001
- Linear Scheduling Model: Development of Controlling Activity PathJournal of Construction Engineering and Management, 1998
- Scheduling Projects with Repeating ActivitiesJournal of Construction Engineering and Management, 1998
- Resource-driven scheduling of repetitive activitiesConstruction Management and Economics, 1998