Digital Integration and Rule-Based Optimization of Workover Hoist Scheduling in a Mature Oil Cluster: A Field Case Study from the Nimr Cluster, Oman

Authors:

Abstract
Challenge: The Nimr Cluster in southern Oman comprises 23 mature fields, more than 3,000 drilled wells and over 1,200 well interventions per year across all job types. Hoist planning previously required planners to extract and reconcile intervention proposals, production deferment, integrity dates and work-order status from five enterprise systems into spreadsheets, consuming approximately two hours per planner per day and producing prioritization that depended on individual judgment. Average restoration cycle time (RCT), the elapsed time from identifying an intervention need to returning the well to production, was 19.4 days in the five months before implementation. Methodology: The Hoist Sequence Optimizer (HSO) entered full production use in July 2025. It integrates enterprise records through a daily-refreshed data pipeline and generates hoist schedules with a transparent, deterministic rule-based method: regional priority categories defined by integrity action code and deferment or gain thresholds, objective-specific greedy construction heuristics, hoist-eligibility and free-interval constraints, and an integrity-deadline repair step with a 15-day planning margin. Planners review, adjust and freeze assignments before execution. HSO does not use machine learning or other artificial-intelligence models. Performance was evaluated by a before-and-after comparison of planning effort and monthly RCT (February–June 2025 versus August 2025–February 2026), with statistical testing and an economic valuation of the RCT change. Results: Recorded planning effort fell by approximately 90%. Mean monthly RCT fell from 19.4 to 15.5 days, a reduction of 3.95 days (20.3%; Welch t-test p = 0.027; 95% confidence interval 0.5–7.4 days), and averaged 14.1 days over October 2025–February 2026. For approximately 32 hoist restoration jobs per month at the field-average rate of 50 bbl/d per well, the 3.95-day reduction brings forward about 6,300 bbl (1,000 m³) of oil per month, equivalent to approximately US$0.5 million of gross revenue per month (about US$6 million per year) at US$80/bbl. A sensitivity analysis bounds this estimate. Novelty: The paper discloses the complete decision logic of an operating, planner-in-the-loop hoist scheduler, namely its input variables, priority categories, ranking criteria, constraints and integrity-repair rule, and links that logic to field-measured RCT and economic outcomes in a large mature onshore cluster. Published workover-scheduling methods are mostly evaluated on computational instances; this study contributes post-implementation field evidence for an explainable rule-based approach that planners can audit and adopt.

This publication has 15 references indexed in Scilit: