A fuzzy optimization model based on improved symmetric tolerance approach is introduced, which allows for rescheduling high‐speed railway timetable under unexpected interferences. The model nests different parameters of the soft constraints with uncertainty margin to describe their importance to the optimization purpose and treats the objective in the same manner. Thus a new optimal instrument is expected to achieve a new timetable subject to little slack of constraints. The section between Nanjing and Shanghai, which is the busiest, of Beijing‐Shanghai high‐speed rail line in China is used as the simulated measurement. The fuzzy optimization model provides an accurate approximation on train running time and headway time, and hence the results suggest that the number of seriously impacted trains and total delay time can be reduced significantly subject to little cost and risk.Keywords
Funding Information
- National Natural Science Foundation of China (61074151, 2009BAG12A10, RCS2009ZT002, RCS2010ZZ002, RCS2011ZZ004)
- National Key Technology Research and Development Program (61074151, 2009BAG12A10, RCS2009ZT002, RCS2010ZZ002, RCS2011ZZ004)
- State Key Laboratory of Rail Traffic Control and Safety (61074151, 2009BAG12A10, RCS2009ZT002, RCS2010ZZ002, RCS2011ZZ004)
- State Key Laboratory of Rail Traffic Control and Safety (61074151, 2009BAG12A10, RCS2009ZT002, RCS2010ZZ002, RCS2011ZZ004)
- State Key Laboratory of Rail Traffic Control and Safety (61074151, 2009BAG12A10, RCS2009ZT002, RCS2010ZZ002, RCS2011ZZ004)
This publication has 32 references indexed in Scilit:
- Optimal inter-area coordination of train rescheduling decisionsTransportation Research Part E: Logistics and Transportation Review, 2012
- Timetabling optimization of a mixed double- and single-tracked railway networkApplied Mathematical Modelling, 2011
- Optimizing the demand captured by a railway system with a regular timetableTransportation Research Part B: Methodological, 2011
- A branch and bound algorithm for scheduling trains in a railway networkEuropean Journal of Operational Research, 2007
- Single-track train timetabling with guaranteed optimality: Branch-and-bound algorithms with enhanced lower boundsTransportation Research Part B: Methodological, 2007
- N-tracked railway traffic re-scheduling during disturbancesTransportation Research Part B: Methodological, 2007
- Railway timetable stability analysis using max-plus system theoryTransportation Research Part B: Methodological, 2007
- Developing railway timetables which guarantee a better serviceEuropean Journal of Operational Research, 2006
- Scheduling trains on a railway network using a discrete event model of railway trafficTransportation Research Part B: Methodological, 2004
- Knowledge-based system for railway schedulingData & Knowledge Engineering, 1998