Jean-Charles Billaut
Current Organizations / Institutes
The organizations/institutes from the scholar's latest article
Previous Organizations / Institutes
The organizations / institutes from the scholar's other articles in the past ten years
Jean-Charles Billaut has a total of 31 co-authors. Here are the top co-authors by number of shared publications:
- Ameur Soukhal
University of Tours
4 shared publications - Azeddine Cheref
Université de Toulouse, INP, CNRS
2 shared publications - Christian Artigues
LAAS-CNRS Université de Toulouse CNRS Toulouse France
2 shared publications - Yannick Kergosien
LIFAT - Laboratoire d'Informatique Fondamentale et Appliquée de Tours (64, Avenue Jean Portalis, 37200 Tours - France)
2 shared publications Alessandro Agnetis
Università degli Studi di Siena
1 shared publication- Alessandro Agnetis
Università degli Studi di Siena
1 shared publication
Latest Publications
- 23 July 2024
- Published by Springer Nature in Journal of Scheduling
- Vol. 27 (5) , 485-505
Scheduling two interfering job sets on identical parallel machines with makespan and total completion time minimization
- 23 July 2024
- Published by Springer Nature in Journal of Scheduling
- Vol. 27 (5) , 485-505
Scheduling two interfering job sets on identical parallel machines with makespan and total completion time minimization
- 1 October 2021
- Published by Springer Nature in Flexible Services and Manufacturing Journal
- Vol. 34 (3) , 785-820
Efficient heuristics to minimize the total tardiness of chemotherapy drug production and delivery
- 1 October 2021
- Published by Springer Nature in Flexible Services and Manufacturing Journal
- Vol. 34 (3) , 785-820
Efficient heuristics to minimize the total tardiness of chemotherapy drug production and delivery
- 8 September 2017
- Published by Springer Nature in Journal of Scheduling
- Vol. 20 (6) , 681-693
Complexity results for an integrated single machine scheduling and outbound delivery problem with fixed sequence
- 8 September 2017
- Published by Springer Nature in Journal of Scheduling
- Vol. 20 (6) , 681-693
Complexity results for an integrated single machine scheduling and outbound delivery problem with fixed sequence
- Open Access
Online recoverable robustness based on groups of permutable jobs for integrated production scheduling and delivery routing
It is well known that the magnitude and the impact on schedule quality of uncertainty in problem data both increase when the integration of scheduling decisions takes place. This paper aims at comparing the standard robust optimization and the recoverable robust optimization frameworks to tackle scenario-based uncertainty in integrated production and distribution scheduling. While the standard robust optimization aims at providing an integrated baseline schedule that optimizes a performance criterion for the worst scenario, the recoverable robustness framework adds a repairing/recovering component, which is able to react to the realized scenario by modifying in a limited way the issued baseline schedule. Hence, the recoverable robustness framework has two merits: it is more realistic, as such repairing elements are often present in practice, and it is able in theory to reach better worst-case performances on the scenario set. However, the question remains whether under limited CPU time, recoverable robustness algorithms are able to actually reach better performance than robust algorithms for reasonable problem instance size. This paper proposes new MILP models and heuristics for a recoverable robust optimization framework based on the concept of groups of permutable jobs and carries out such a comparison on a one-machine production facility coupled with a single vehicle distribution system. For this problem, the experimental results exhibit conditions under which a recoverable robust approach is likely to yield better results than the standard robust approach.
Open AccessOnline recoverable robustness based on groups of permutable jobs for integrated production scheduling and delivery routing
It is well known that the magnitude and the impact on schedule quality of uncertainty in problem data both increase when the integration of scheduling decisions takes place. This paper aims at comparing the standard robust optimization and the recoverable robust optimization frameworks to tackle scenario-based uncertainty in integrated production and distribution scheduling. While the standard robust optimization aims at providing an integrated baseline schedule that optimizes a performance criterion for the worst scenario, the recoverable robustness framework adds a repairing/recovering component, which is able to react to the realized scenario by modifying in a limited way the issued baseline schedule. Hence, the recoverable robustness framework has two merits: it is more realistic, as such repairing elements are often present in practice, and it is able in theory to reach better worst-case performances on the scenario set. However, the question remains whether under limited CPU time, recoverable robustness algorithms are able to actually reach better performance than robust algorithms for reasonable problem instance size. This paper proposes new MILP models and heuristics for a recoverable robust optimization framework based on the concept of groups of permutable jobs and carries out such a comparison on a one-machine production facility coupled with a single vehicle distribution system. For this problem, the experimental results exhibit conditions under which a recoverable robust approach is likely to yield better results than the standard robust approach.
- Open Access
Fixed-sequence Single Machine Scheduling and Outbound Delivery Problems
In this paper, we consider an integrated production and outbound delivery scheduling problem. In particular, we address the situation in which the scheduling sequence and the delivery sequence are the same and predefined. A set of jobs are processed on a single machine and finished jobs are delivered to the customers by a single capacitated vehicle. Each job has a processing time and transportation times between customers are taken into account. Since the sequence is given, the problem consists to form batches of jobs and our objective is to minimize the sum of the delivery times or general functions of the delivery times. The NP-hardness of the general problem is established and a pseudopolynomial time dynamic programming algorithm is given. Some particular cases are treated, for which complexity proofs or polynomial time algorithms are given.
Open AccessFixed-sequence Single Machine Scheduling and Outbound Delivery Problems
In this paper, we consider an integrated production and outbound delivery scheduling problem. In particular, we address the situation in which the scheduling sequence and the delivery sequence are the same and predefined. A set of jobs are processed on a single machine and finished jobs are delivered to the customers by a single capacitated vehicle. Each job has a processing time and transportation times between customers are taken into account. Since the sequence is given, the problem consists to form batches of jobs and our objective is to minimize the sum of the delivery times or general functions of the delivery times. The NP-hardness of the general problem is established and a pseudopolynomial time dynamic programming algorithm is given. Some particular cases are treated, for which complexity proofs or polynomial time algorithms are given.
- 5 February 2015
- Published by Springer Nature in Journal of Intelligent Manufacturing
- Vol. 29 (3) , 617-628
Matheuristic algorithms for minimizing total tardiness in the m-machine flow-shop scheduling problem
- 5 February 2015
- Published by Springer Nature in Journal of Intelligent Manufacturing
- Vol. 29 (3) , 617-628
Matheuristic algorithms for minimizing total tardiness in the m-machine flow-shop scheduling problem
- 7 March 2014
- Published by EDP Sciences in RAIRO - Operations Research
- Vol. 48 (2) , 255-269
Solving multi-agent scheduling problems on parallel machines with a global objective function
- 7 March 2014
- Published by EDP Sciences in RAIRO - Operations Research
- Vol. 48 (2) , 255-269
Solving multi-agent scheduling problems on parallel machines with a global objective function
- 30 September 2011
- Published by Elsevier in International Journal of Medical Informatics
- Vol. 80 (9) , 655-662
Planning and tracking chemotherapy production for cancer treatment: A performing and integrated solution
- 30 September 2011
- Published by Elsevier in International Journal of Medical Informatics
- Vol. 80 (9) , 655-662
Planning and tracking chemotherapy production for cancer treatment: A performing and integrated solution
- 21 September 2011
- Published by Springer Nature in Journal of Scheduling
- Vol. 15 (3) , 311-321
Single-machine multi-agent scheduling problems with a global objective function
- 21 September 2011
- Published by Springer Nature in Journal of Scheduling
- Vol. 15 (3) , 311-321
Single-machine multi-agent scheduling problems with a global objective function
- 1 May 2010
- Published by Elsevier in European Journal of Operational Research
- Vol. 202 (3) , 646-653
A new dynamic programming formulation for scheduling independent tasks with common due date on parallel machines
- 1 May 2010
- Published by Elsevier in European Journal of Operational Research
- Vol. 202 (3) , 646-653
A new dynamic programming formulation for scheduling independent tasks with common due date on parallel machines