PLPertti Lahdenperä

Pertti Lahdenperä

*This is an algorithmically generated author record based on publicly available information.

Current Organizations / Institutes

The organizations/institutes from the scholar's latest article


Pertti Lahdenperä has a total of 16 co-authors. Here are the top co-authors by number of shared publications:


Latest Publications

  • Formularising alternative two-stage target-cost arrangements for projects with development and risk mitigation potential

    by Pertti Lahdenperä

    A two-stage target-cost (2STC) contract has been proposed to advance efficient pricing in collaborative projects where a project team is involved in the project early on (with a commitment to a certain target cost level) to improve its value-for-money in a separate development phase (after which the target cost and risk allocation may be altered) before entering to implementation. However, so far, 2STC solutions have only been formularised for projects where there is a lot of uncertainty left in the implementation phase requiring the use of joint risk-sharing principles (a target cost system) until the completion of the project. The purpose of this paper is to discover whether a similar form of incentivisation could be developed for more straightforward projects, where the starting point is a target cost or guaranteed maximum price contract initially, but the implementation phase may follow (or move towards) a more common risk-transfer practice (a fixed price contract) because of a successful development phase providing improved cost efficiency and reduced uncertainty. By means of design science the study establishes two concrete 2STC payment system formulations that are shown to function as intended, with certain reservations. Therefore, the study contributes by extending the potential application area of a 2STC strategy to new types of projects by enabling them to benefit from the parties’ combined know-how while fostering development and efficient pricing also from the view of the project owner.

  • Open Access

    Design–build with a development phase: An initiation and the first trials

    by Pertti Lahdenperä

    Design–build (DB) is a much used project delivery system with operational variations for different needs and situations. Yet, novel applications have to be strived for as all of the current applications have some drawbacks. Accordingly, this study focuses on a DB procedure that exploits the parties’ collaboration in order to improve the economic efficiency of construction projects. It is called “design–build with a development phase” (DBd). In the procedure, the owner and the selected contractor continue the development of the project solution in co-operation, adhering to the principle of benefit sharing, which is enabled by the benchmark solution, formed as a result of price-inclusive contractor selection. More precisely, this paper presents the DBd procedure and how it was initially constructed and eventually applied in a few infrastructure projects. The paper also reports the related experiences, which were positive based on the improved value for money in the trial projects. Thus, the paper contributes by disproving the dominant view, which has been guiding the formulation and use of the current project delivery practices, that price-inclusive competition and collaborative development thereafter could not be matched successfully.


  • Open Access

    Relational contracting in Nordic construction – a comparative longitudinal account of institutional field developments

    by Anna Kadefors, Kirsi Aaltonen, Stefan Christoffer Gottlieb, Ole Jonny Klakegg, Pertti Lahdenperä, Nils O.E. Olsson, Lilly Rosander, Christian Thuesen

    Purpose: Relational contracting is increasingly being applied to complex and uncertain construction projects. However, it has proved hard to achieve stable performance and industry-level learning in this field. This paper employs an institutional perspective to analyze how legitimacy for relational contracting has been produced and challenged in Denmark, Finland, Norway and Sweden, including implications for dissemination and learning.Design/methodology/approach: A collaborative case study design is used, where longitudinal accounts of the developments in relational contracting over more than 25 years in four Nordic countries were developed by scholars based in each country. The descriptions are underpinned by literature sources from research, practice and policy.Findings: The countries share similar problem perceptions that have triggered the de-institutionalization of traditional contracting practices. Models and policies developed elsewhere are important sources of knowledge and legitimacy. Most countries have seen pendulum movements, where dissemination of relational contracting is followed by backlashes when projects fail to meet projected outcomes. Before long, however, relational contracting tends to re-emerge under new labels and in slightly new forms. Such a proliferation of concepts presents further obstacles to learning. Successful institutionalization is found to rely on realistic goals in combination with broad competence development at the organizational and industry levels.Practical implications: In seeking inspiration from other countries, policymakers should go beyond contract models to also consider strategies to manage industry-level learning.Originality/value: The paper provides a unique longitudinal cross-country perspective on the field of relational contracting. As such, it contributes to the small stream of literature on long-term institutional change in the construction sector.


  • Dimensions of governance in interorganizational project networks

    by Jaakko Kujala, Kirsi Aaltonen, Nadezhda Gotcheva, Pertti Lahdenperä

    Purpose: The purpose of this study is to create a framework to analyze approaches for coordination, adaptation and safeguarding of exchanges in interorganizational project networks.Design/methodology/approach: An analysis framework to analyze governance in project networks was created based on a systematic review of existing literature. The framework was applied to analyze governance approaches used in a large infrastructure project implemented with an alliance project delivery method to illustrate the practical validity of the framework.Findings: The analysis framework categorized governance in project networks in six dimensions: goal setting, rewarding, monitoring, roles and decision-making, coordination and capability building. A set of questions for each governance dimension was created and the analysis framework was applied in the context of a project alliance.Research limitations/implications: The focus of this research is on governance internal to a project network. The authors identified dimensions of governance in project networks and related governance approaches based on a systematic literature review. The practical applicability of the framework was validated in a single case study setting.Practical implications: The paper introduces a concept of governance in project networks, which takes the perspective that all actors that have an influence on project implementation are part of an interorganizational project network. The focal organization may have had a significant role in the design of governance, but governance also emerged from the network structure of companies and the interactions among them. The analysis framework created in this research can be used to design and analyze governance in different type of project context.Originality/value: The paper introduces a concept of governance in project networks, which takes the perspective that all actors that have an influence on project implementation are part of an interorganizational project network.


  • Digital Situation Picture in Construction – Case of Prefabricated Structural Elements

    by Rita Lavikka, Pertti Lahdenperä, Markku Kiviniemi, Antti Peltokorpi


  • Key features of a project alliance and their impact on the success of an apartment renovation: a case study

    by Daniel Amaral Fernandes, António Aguiar Costa, Pertti Lahdenperä

    With a view to becoming more efficient and cost-effective, the construction sector has been focusing more and more on developing new delivery and collaborative procurement procedures, such as project alliances. Until now, project alliances have focused mostly on large-scale road, rail and water infrastructure projects. Despite the positive results achieved in these projects, the building and real estate sector has been rather reluctant to use this delivery method. The objective of this study was to find out whether it makes sense to use project alliancing in more everyday projects. The chosen case study is a renovation construction project in Finland that was contracted using the project alliance approach. In order to have a comprehensive understanding of the issues involved, a literature review was conducted and case project-specific documentation analysed. Subsequently, several interviews were conducted with project participants, paying particular attention to the experiences and feedback obtained from developer, contractor and designer sides. In terms of the project participants’ perspectives, the alliance was unanimously seen as an asset which contributed to high levels of collaboration between participants and made it possible to achieve positive results.


  • Open Access

    Towards a Coherent Theory of Project Alliancing: Discovering the System’s Complex Mechanisms Yielding Value for Money

    by Pertti Lahdenperä

    Alliancing is a relatively new construction project delivery method receiving increasing interest globally while also eliciting many questions about its effectiveness. That is why its operating logic should be clarified beyond the currently existing general views. Correspondingly, this paper aims to define the means and mechanisms which influence the capacity of alliancing to produce value for money. The work establishes the interlaced impact chains between formal basic solutions of alliancing and the key result areas defining the value-for-money ratio. This is made by focussing on a single alliance project and its procedural solutions and experiences. The case project of the study was an urban road tunnel under a city structure and the impact chains were explored by interviewing all eight members of the alliance leadership team covering all contracting parties. The two-stage personal interviews were conducted in accordance with the systematic modelling procedure resulting in eight cognitive maps which were then combined into a group map. The resulting model included around one hundred interlinked concepts initially, but was streamlined for the paper. Accordingly, alliancing offers a concrete framework which gives better than normal chances of success in the case of complex, challenging projects fraught with much uncertainty. Many diverse basic alliance solutions/features contribute to success, while each feature also seems to strengthen the impact of the others. This suggests that, at its best, pure project alliance is not only a coherent but also a holistic solution to challenging projects.