Ying Hong
Current Organizations / Institutes
The organizations/institutes from the scholar's latest article
Previous Organizations / Institutes
The organizations / institutes from the scholar's other articles in the past ten years
Research Subjects
Ying Hong has a total of 26 co-authors. Here are the top co-authors by number of shared publications:
- Ali Akbarnezhad
The University of New South Wales
4 shared publications - Ioannis Brilakis
Univ. of Cambridge
4 shared publications - Ahmed W. A. Hammad
School of Built Environment, University of New South Wales, Kensington, Sydney, NSW 2052, Australia
3 shared publications - Haiyan Xie
Department of Technology, Illinois State University, Normal, Il 61790, USA
2 shared publications - Saleh Mohammad Ebrahimzadeh Sepasgozar
School of Built Environment, University of New South Wales
2 shared publications Ahmed Hammad
Lecturer, Faculty of Built Environment, Univ. of New South Wales, Sydney, NSW 2052, Australia
1 shared publication
Latest Publications
- Open Access
- 26 February 2024
- Published by Elsevier in Building and Environment
- Vol. 253, 111359
Visualising a framework for enhancing material circularity in building construction projects: Drivers, barriers, and strategies
- 26 February 2024
- Published by Elsevier in Building and Environment
- Vol. 253, 111359
Open AccessVisualising a framework for enhancing material circularity in building construction projects: Drivers, barriers, and strategies
- Open Access
- 1 February 2023
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 149 (2) , 05022020
Graph-Based Automated Construction Scheduling without the Use of BIM
The construction industry has been suffering from delays and cost overruns for decades. Experienced schedulers programs and allocate contingencies (both cost and time) based on professional experiences and gained knowledge. Such tacit knowledge has not been captured, stored, and shared with inexperienced schedulers. This paper proposes a graph-based automated scheduling (GAS) method to capture, store, and reuse the tacit knowledge in the construction schedules. The proposed GAS method takes construction schedules as input, extracts schedule features, classifies schedules into different types of sequences, selects and assembles sequences into schedules, and eventually optimizes time- and cost-efficiency of assembled schedules. The GAS method was validated on two case studies. The results indicated that the automatically generated construction schedule is, on average, 6.70% closer to the actual schedule than the planned schedule. Different from existing automatic scheduling methods, GAS relies little on the availability and data richness of building information modeling (BIM) models. Hence, GAS helps schedulers initiate new schedules more efficiently at the early construction stages.
- 1 February 2023
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 149 (2) , 05022020
Open AccessGraph-Based Automated Construction Scheduling without the Use of BIM
The construction industry has been suffering from delays and cost overruns for decades. Experienced schedulers programs and allocate contingencies (both cost and time) based on professional experiences and gained knowledge. Such tacit knowledge has not been captured, stored, and shared with inexperienced schedulers. This paper proposes a graph-based automated scheduling (GAS) method to capture, store, and reuse the tacit knowledge in the construction schedules. The proposed GAS method takes construction schedules as input, extracts schedule features, classifies schedules into different types of sequences, selects and assembles sequences into schedules, and eventually optimizes time- and cost-efficiency of assembled schedules. The GAS method was validated on two case studies. The results indicated that the automatically generated construction schedule is, on average, 6.70% closer to the actual schedule than the planned schedule. Different from existing automatic scheduling methods, GAS relies little on the availability and data richness of building information modeling (BIM) models. Hence, GAS helps schedulers initiate new schedules more efficiently at the early construction stages.
- 12 June 2022
- Published by Elsevier in Advanced Engineering Informatics
- Vol. 53
Improving the accuracy of schedule information communication between humans and data
- 12 June 2022
- Published by Elsevier in Advanced Engineering Informatics
- Vol. 53
Improving the accuracy of schedule information communication between humans and data
- Open Access
- 1 April 2022
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 148 (4) , 05022002
Analysis of User Needs in Time-Related Risk Management for Holistic Project Understanding
Evaluation of time-related risks often leads to changes and adjustments in construction schedules, but this influential process is not extensively mapped in literature because of the unstructured data. This absence causes information deficiency and confusion in communication, which, in turn, affects project planning and control, and hinders knowledge sharing and management. This research aims to investigate the obstacles in project execution with the assumption that a decision tree model can map user needs and trace workflows. To understand user needs, we first recorded the focus group discussions followed by semi-structured interviews, then transcribed them into a combined script of 120,000 words. Meanwhile, the prevailing standards of project execution were diagrammed to define ten interconnected categories and derive the workflow schemes to obtain a novel decision tree model, which was used together with the interview data to validate the probabilities and the weighted significance values. The next step was to quantify and prioritize the exact user needs and data specifications of the industry professionals during project execution. After the verification with the invited expert panel, the results show that the most predominant urgencies of time-related risk management are (1) the decision support tools using automated functions to check schedule logic and evaluating risks, (2) preparation assistance for risk communication, and (3) generation of risk mitigation scenarios. The findings can help to line up software development steps for scheduling programs and improve the quality of the risk response strategies for construction projects. One limitation of the current work is the sample size of interviewees, which could be enhanced by designing a questionnaire based on the findings and survey the construction industry.
- 1 April 2022
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 148 (4) , 05022002
Open AccessAnalysis of User Needs in Time-Related Risk Management for Holistic Project Understanding
Evaluation of time-related risks often leads to changes and adjustments in construction schedules, but this influential process is not extensively mapped in literature because of the unstructured data. This absence causes information deficiency and confusion in communication, which, in turn, affects project planning and control, and hinders knowledge sharing and management. This research aims to investigate the obstacles in project execution with the assumption that a decision tree model can map user needs and trace workflows. To understand user needs, we first recorded the focus group discussions followed by semi-structured interviews, then transcribed them into a combined script of 120,000 words. Meanwhile, the prevailing standards of project execution were diagrammed to define ten interconnected categories and derive the workflow schemes to obtain a novel decision tree model, which was used together with the interview data to validate the probabilities and the weighted significance values. The next step was to quantify and prioritize the exact user needs and data specifications of the industry professionals during project execution. After the verification with the invited expert panel, the results show that the most predominant urgencies of time-related risk management are (1) the decision support tools using automated functions to check schedule logic and evaluating risks, (2) preparation assistance for risk communication, and (3) generation of risk mitigation scenarios. The findings can help to line up software development steps for scheduling programs and improve the quality of the risk response strategies for construction projects. One limitation of the current work is the sample size of interviewees, which could be enhanced by designing a questionnaire based on the findings and survey the construction industry.
- Open Access
- 13 January 2022
- Published by International Council for Research and Innovation in Building and Construction in Journal of Information Technology in Construction
- Vol. 27 (4) , 70-93
Construction schedule risk analysis – a hybrid machine learning approach
The UK commissions about £100 billion in infrastructure construction works every year. More than 50% of them finish later than planned, causing damage to the interests of stakeholders. The estimation of time-risk on construction projects is currently done subjectively, largely by experience despite there are many existing techniques available to analyse risk on the construction schedules. Unlike conventional methods that tend to depend on the accurate estimation of risk boundaries for each task, this research aims to proposes a hybrid method to assist planners in undertaking risk analysis using baseline schedules with improved accuracy. The proposed method is endowed with machine intelligence and is trained using a database of 293,263 tasks from a diverse sample of 302 completed infrastructure construction projects in the UK. It combines a Gaussian Mixture Modelling-based Empirical Bayesian Network and a Support Vector Machine followed by performing a Monte Carlo risk simulation. The former is used to investigate the uncertainty, correlated risk factors, and predict task duration deviations while the latter is used to return a time-risk simulated prediction. This study randomly selected 10 projects as case studies followed by comparing their results of the proposed hybrid method with Monte Carlo Simulation. Results indicated 54.4% more accurate prediction on project delays.
- 13 January 2022
- Published by International Council for Research and Innovation in Building and Construction in Journal of Information Technology in Construction
- Vol. 27 (4) , 70-93
Open AccessConstruction schedule risk analysis – a hybrid machine learning approach
The UK commissions about £100 billion in infrastructure construction works every year. More than 50% of them finish later than planned, causing damage to the interests of stakeholders. The estimation of time-risk on construction projects is currently done subjectively, largely by experience despite there are many existing techniques available to analyse risk on the construction schedules. Unlike conventional methods that tend to depend on the accurate estimation of risk boundaries for each task, this research aims to proposes a hybrid method to assist planners in undertaking risk analysis using baseline schedules with improved accuracy. The proposed method is endowed with machine intelligence and is trained using a database of 293,263 tasks from a diverse sample of 302 completed infrastructure construction projects in the UK. It combines a Gaussian Mixture Modelling-based Empirical Bayesian Network and a Support Vector Machine followed by performing a Monte Carlo risk simulation. The former is used to investigate the uncertainty, correlated risk factors, and predict task duration deviations while the latter is used to return a time-risk simulated prediction. This study randomly selected 10 projects as case studies followed by comparing their results of the proposed hybrid method with Monte Carlo Simulation. Results indicated 54.4% more accurate prediction on project delays.
- 1 November 2020
- Published by Elsevier in Automation in Construction
- Vol. 119
A neural network approach to predicting the net costs associated with BIM adoption
- 1 November 2020
- Published by Elsevier in Automation in Construction
- Vol. 119
A neural network approach to predicting the net costs associated with BIM adoption
- 1 February 2020
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 146 (2)
Comparative Modeling Approach to Capture the Differences in BIM Adoption Decision-Making Process in Australia and China
The growing rate of building information modeling (BIM) adoption inevitability adds to the importance of understanding the BIM adoption decision-making process. Several models based on systematic surveys are available in the literature to formulate the BIM adoption decision-making process. It is still, however, not clear whether the decision parameters in these models are universally important. This study examines the main attributes of the BIM adoption decision-making process in China and Australia. An adoption model developed earlier for Australia is tested for Chinese data collected from 103 small and medium construction companies (SMEs). By highlighting model fitness issues, the model is then reconstructed for comparing BIM adoption in cross-cultural contexts. Data are analyzed using a logistic regression to understand the main factors impacting BIM adoption. Structural equation modeling based on multigroup analysis is also adopted in the analysis. The analysis indicates that Australian construction SMEs adopt BIM to solve organizational collaboration problems and improve workflow efficiency, whereas Chinese construction SMEs adopt BIM to improve organizational technical ability. The results of this study highlighted the Chinse companies tend to be more careful during the implementation of new technology to minimize uncertainty, whereas BIM adoption decision makers in Australian companies are more focused on change management and empowering subordinates.
- 1 February 2020
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 146 (2)
Comparative Modeling Approach to Capture the Differences in BIM Adoption Decision-Making Process in Australia and China
The growing rate of building information modeling (BIM) adoption inevitability adds to the importance of understanding the BIM adoption decision-making process. Several models based on systematic surveys are available in the literature to formulate the BIM adoption decision-making process. It is still, however, not clear whether the decision parameters in these models are universally important. This study examines the main attributes of the BIM adoption decision-making process in China and Australia. An adoption model developed earlier for Australia is tested for Chinese data collected from 103 small and medium construction companies (SMEs). By highlighting model fitness issues, the model is then reconstructed for comparing BIM adoption in cross-cultural contexts. Data are analyzed using a logistic regression to understand the main factors impacting BIM adoption. Structural equation modeling based on multigroup analysis is also adopted in the analysis. The analysis indicates that Australian construction SMEs adopt BIM to solve organizational collaboration problems and improve workflow efficiency, whereas Chinese construction SMEs adopt BIM to improve organizational technical ability. The results of this study highlighted the Chinse companies tend to be more careful during the implementation of new technology to minimize uncertainty, whereas BIM adoption decision makers in Australian companies are more focused on change management and empowering subordinates.
- 24 March 2019
- Published by Taylor & Francis in Construction Management and Economics
- Vol. 37 (11) , 675-691
Impact of organization size and project type on BIM adoption in the Chinese construction market
Building Information Modelling (BIM) is perceived as an effective tool for improving the delivery and coordination of construction projects. The Chinese construction sector has demonstrated significant interest in implementing the 3-dimensional modelling-based process. BIM adoption is influenced by several factors which can either be operational or strategic related. Factors which can have a significant impact include the size of the construction organization and the type of projects that the organization has to deliver (i.e. building vs infrastructure projects). This study aims to evaluate the effect of project type and size on BIM adoption in the Chinese market, via an adoption model which analyses factors impacting the adoption decision. The study examines 200 samples collected from the Chinese construction industry, split equally between infrastructure and building construction data groups, as well as SMEs and large organizations. The collected data are first analyzed by principal component analysis and then through a Structural Equation Modelling-based multiple group analysis. Results demonstrate that essential factors such as operational risks are considered by small organization, whereas large organizations focus on implementation challenges. Implementation benefits and challenges are significant on the adoption decision in infrastructure organizations, but not in building organizations. In addition, the study reveals that “technical support” is an important factor when it comes to BIM adoption among all types of organizations, regardless of the organization’s size and project type delivered.
- 24 March 2019
- Published by Taylor & Francis in Construction Management and Economics
- Vol. 37 (11) , 675-691
Impact of organization size and project type on BIM adoption in the Chinese construction market
Building Information Modelling (BIM) is perceived as an effective tool for improving the delivery and coordination of construction projects. The Chinese construction sector has demonstrated significant interest in implementing the 3-dimensional modelling-based process. BIM adoption is influenced by several factors which can either be operational or strategic related. Factors which can have a significant impact include the size of the construction organization and the type of projects that the organization has to deliver (i.e. building vs infrastructure projects). This study aims to evaluate the effect of project type and size on BIM adoption in the Chinese market, via an adoption model which analyses factors impacting the adoption decision. The study examines 200 samples collected from the Chinese construction industry, split equally between infrastructure and building construction data groups, as well as SMEs and large organizations. The collected data are first analyzed by principal component analysis and then through a Structural Equation Modelling-based multiple group analysis. Results demonstrate that essential factors such as operational risks are considered by small organization, whereas large organizations focus on implementation challenges. Implementation benefits and challenges are significant on the adoption decision in infrastructure organizations, but not in building organizations. In addition, the study reveals that “technical support” is an important factor when it comes to BIM adoption among all types of organizations, regardless of the organization’s size and project type delivered.
- Open Access
- 1 January 2019
- Published by International Council for Research and Innovation in Building and Construction in Journal of Information Technology in Construction
- Vol. 24 (33) , 588-603
Forecasting the net costs to organisations of Building Information Modelling (BIM) implementation at different levels of development (LOD)
Numerous frameworks and tools have been proposed in the literature to assess the performance of BIM implementation in the Architecture, Engineering and Construction (AEC). However, there is yet a lack of ex-ante evaluation methods that forecast BIM implementation costs. This study aims to propose an ex-ante evaluation method to forecast the net costs of BIM implementation at different Level of Development (LOD). The proposed method is expected to assist decision makers to find the most cost-saving LOD when investing resources for implementing BIM, from an organisational perspective. The proposed method relies on an Artificial Neural Network (ANN) for each type of implementation costs and benefits. The findings suggest that decision makers need to evaluate an organisation’s competency and their implemented BIM applications when choosing the BIM implementation level of BIM. Furthermore, the results show that a higher BIM implementation level does not often secure more benefits. Over 30 features were included in the ANNs with results indicating the possibility of expanding the feature set to obtain more accurate results.
- 1 January 2019
- Published by International Council for Research and Innovation in Building and Construction in Journal of Information Technology in Construction
- Vol. 24 (33) , 588-603
Open AccessForecasting the net costs to organisations of Building Information Modelling (BIM) implementation at different levels of development (LOD)
Numerous frameworks and tools have been proposed in the literature to assess the performance of BIM implementation in the Architecture, Engineering and Construction (AEC). However, there is yet a lack of ex-ante evaluation methods that forecast BIM implementation costs. This study aims to propose an ex-ante evaluation method to forecast the net costs of BIM implementation at different Level of Development (LOD). The proposed method is expected to assist decision makers to find the most cost-saving LOD when investing resources for implementing BIM, from an organisational perspective. The proposed method relies on an Artificial Neural Network (ANN) for each type of implementation costs and benefits. The findings suggest that decision makers need to evaluate an organisation’s competency and their implemented BIM applications when choosing the BIM implementation level of BIM. Furthermore, the results show that a higher BIM implementation level does not often secure more benefits. Over 30 features were included in the ANNs with results indicating the possibility of expanding the feature set to obtain more accurate results.
- 16 August 2018
- Published by Emerald Publishing in Engineering, Construction and Architectural Management
- Vol. 26 (2) , 154-183
BIM adoption model for small and medium construction organisations in Australia
Purpose: The purpose of this paper is to present a model for building information modelling (BIM) implementation at small and medium-sized construction contractor organisations (SMOs). The proposed BIM adoption model assesses BIM implementation benefits, costs and challenges faced by SMOs. Correlation between BIM adoption in SMOs and the associated impacting factors, including knowledge support and BIM adoption motivation, is captured through the model. Design/methodology/approach: A literature review of BIM adoption in construction was first presented. Research data, collected from 80 SMOs in Australia through a conducted survey, are then analysed. Descriptive analysis and structural equation modelling were used to investigate SMOs’ understanding of BIM, and to qualify the correlations among the proposed latent variables impacting BIM implementation at SMOs, respectively. Additionally, this study used χ2 test to compare differences between BIM users and non-BIM users regarding BIM understanding, interested applications and attitudes towards implementation benefits and challenges. Findings: Potential benefits associated with BIM implementation are a major motivation factor when it comes to BIM adoption at SMOs. In addition, existing staff’s capability in using BIM tools positively affects the establishment of an organisational knowledge-support system, which determines the decision of adopting BIM eventually. Ultimately, there is a need for further emphasis on staff engagement in the implementation process. Research limitations/implications: The results presented in this paper are applicable to SMOs in the building sector of construction. BIM implementation at organisations involved in non-building activities, including civil works and infrastructure, needs to be assessed in the future. Practical implications: The results indicate that rather than placing the focus mainly on benefits of BIM implementation, successful implementation of BIM in practice requires adequate effort to assess implementation problems, establish knowledge support and engage staff in using BIM. Originality/value: Results of this study provide an insight into the adoption challenges of BIM in SMOs, given that the focus of previous studies has been mostly placed on BIM adoption in architectural firms and large contractors.
- 16 August 2018
- Published by Emerald Publishing in Engineering, Construction and Architectural Management
- Vol. 26 (2) , 154-183
BIM adoption model for small and medium construction organisations in Australia
Purpose: The purpose of this paper is to present a model for building information modelling (BIM) implementation at small and medium-sized construction contractor organisations (SMOs). The proposed BIM adoption model assesses BIM implementation benefits, costs and challenges faced by SMOs. Correlation between BIM adoption in SMOs and the associated impacting factors, including knowledge support and BIM adoption motivation, is captured through the model. Design/methodology/approach: A literature review of BIM adoption in construction was first presented. Research data, collected from 80 SMOs in Australia through a conducted survey, are then analysed. Descriptive analysis and structural equation modelling were used to investigate SMOs’ understanding of BIM, and to qualify the correlations among the proposed latent variables impacting BIM implementation at SMOs, respectively. Additionally, this study used χ2 test to compare differences between BIM users and non-BIM users regarding BIM understanding, interested applications and attitudes towards implementation benefits and challenges. Findings: Potential benefits associated with BIM implementation are a major motivation factor when it comes to BIM adoption at SMOs. In addition, existing staff’s capability in using BIM tools positively affects the establishment of an organisational knowledge-support system, which determines the decision of adopting BIM eventually. Ultimately, there is a need for further emphasis on staff engagement in the implementation process. Research limitations/implications: The results presented in this paper are applicable to SMOs in the building sector of construction. BIM implementation at organisations involved in non-building activities, including civil works and infrastructure, needs to be assessed in the future. Practical implications: The results indicate that rather than placing the focus mainly on benefits of BIM implementation, successful implementation of BIM in practice requires adequate effort to assess implementation problems, establish knowledge support and engage staff in using BIM. Originality/value: Results of this study provide an insight into the adoption challenges of BIM in SMOs, given that the focus of previous studies has been mostly placed on BIM adoption in architectural firms and large contractors.