Zach Barr
Research Subjects
Zach Barr has a total of 6 co-authors. Here are the top co-authors by number of shared publications:
- Anna West
Kearns & West, Inc., San Francisco, CA 94104, USA
3 shared publications - Craig Jones
Integral Consulting Inc., Santa Cruz, CA 95060, USA
3 shared publications - Jesse Roberts
Sandia National Laboratories, Albuquerque, NM 87123, USA
3 shared publications - Sharon Kramer
H. T. Harvey & Associates, Arcata, CA 95521, USA
3 shared publications - Geoffrey Taylor Klise
Sandia National Laboratories (SNL-NM), Albuquerque, NM (United States)
2 shared publications - William John Peplinski
Sandia National Laboratories (SNL-NM), Albuquerque, NM (United States)
2 shared publications
Latest Publications
- Open Access
The Permitting, Licensing and Environmental Compliance Process: Lessons and Experiences within U.S. Marine Renewable Energy
The marine renewable energy (MRE; renewable energy captured from waves, tides, ocean currents, the natural flow of water in rivers, and marine thermal gradients, without building new dams or diversions) industry has a vital role in the U.S. clean energy strategy as we progress to meet U.S. electricity and blue economy needs with renewable, domestic energy sources. However, a thorough assessment of the U.S. marine energy permitting process from the viewpoints of both developers that propose projects and regulators that permit them has not been performed. Sharing practical experiences in this new industry is vital to increase the efficiency and effectiveness of the permitting process, identify data and information gaps, develop lessons learned, and advance the industry. This paper is a case study of qualitative findings, lessons learned, and recommendations from guided discussions, workshops, and webinars with both marine renewable energy developers and state and federal regulators that have experience in the permitting process in the U.S.
Open AccessThe Permitting, Licensing and Environmental Compliance Process: Lessons and Experiences within U.S. Marine Renewable Energy
The marine renewable energy (MRE; renewable energy captured from waves, tides, ocean currents, the natural flow of water in rivers, and marine thermal gradients, without building new dams or diversions) industry has a vital role in the U.S. clean energy strategy as we progress to meet U.S. electricity and blue economy needs with renewable, domestic energy sources. However, a thorough assessment of the U.S. marine energy permitting process from the viewpoints of both developers that propose projects and regulators that permit them has not been performed. Sharing practical experiences in this new industry is vital to increase the efficiency and effectiveness of the permitting process, identify data and information gaps, develop lessons learned, and advance the industry. This paper is a case study of qualitative findings, lessons learned, and recommendations from guided discussions, workshops, and webinars with both marine renewable energy developers and state and federal regulators that have experience in the permitting process in the U.S.
- Open Access
Marine Energy Environmental Permitting and Compliance Costs
Costs to permit Marine Energy projects are poorly understood. In this paper we examine environmental compliance and permitting costs for 19 projects in the U.S., covering the last 2 decades. Guided discussions were conducted with developers over a 3-year period to obtain historical and ongoing project cost data relative to environmental studies (e.g., baseline or pre-project site characterization as well as post-installation effects monitoring), stakeholder outreach, and mitigation, as well as qualitative experience of the permitting process. Data are organized in categories of technology type, permitted capacity, pre- and post-installation, geographic location, and funding types. We also compare our findings with earlier logic models created for the Department of Energy (i.e., Reference Models). Environmental studies most commonly performed were for Fish and Fisheries, Noise, Marine Habitat/Benthic Studies and Marine Mammals. Studies for tidal projects were more expensive than those performed for wave projects and the range of reported project costs tended to be wider than ranges predicted by logic models. For eight projects reporting full project costs, from project start to FERC or USACE permit, the average amount for environmental permitting compliance was 14.6%.
Open AccessMarine Energy Environmental Permitting and Compliance Costs
Costs to permit Marine Energy projects are poorly understood. In this paper we examine environmental compliance and permitting costs for 19 projects in the U.S., covering the last 2 decades. Guided discussions were conducted with developers over a 3-year period to obtain historical and ongoing project cost data relative to environmental studies (e.g., baseline or pre-project site characterization as well as post-installation effects monitoring), stakeholder outreach, and mitigation, as well as qualitative experience of the permitting process. Data are organized in categories of technology type, permitted capacity, pre- and post-installation, geographic location, and funding types. We also compare our findings with earlier logic models created for the Department of Energy (i.e., Reference Models). Environmental studies most commonly performed were for Fish and Fisheries, Noise, Marine Habitat/Benthic Studies and Marine Mammals. Studies for tidal projects were more expensive than those performed for wave projects and the range of reported project costs tended to be wider than ranges predicted by logic models. For eight projects reporting full project costs, from project start to FERC or USACE permit, the average amount for environmental permitting compliance was 14.6%.
- Open Access
- 24 July 2020
- Published by MDPI AG in Journal of Marine Science and Engineering
- Vol. 8 (8) , 554
Environmental Permitting and Compliance Cost Reduction Strategies for the MHK Industry: Lessons Learned from Other Industries
The marine and hydrokinetic (MHK) industry plays a vital role in the U.S. clean energy strategy by providing a renewable, domestic energy source that may offset the need for traditional energy sources. The first MHK deployments in the U.S. have incurred very high permitting costs and long timelines for deploying projects, which increases project risk and discourages investment. A key challenge to advancing an economically competitive U.S. MHK industry is reducing the time and cost required for environmental permitting and compliance with government regulations. Other industries such as offshore oil and gas, offshore wind energy, subsea power and data cables, onshore wind energy, and solar energy facilities have all developed more robust permitting and compliance pathways that provide lessons for the MHK industry in the U.S. and may help inform the global consenting process. Based on in-depth review and research into each of the other industries, we describe the environmental permitting pathways, the main environmental concerns and types of monitoring typically associated with them, and factors that appear to have eased environmental permitting and compliance issues.
- 24 July 2020
- Published by MDPI AG in Journal of Marine Science and Engineering
- Vol. 8 (8) , 554
Open AccessEnvironmental Permitting and Compliance Cost Reduction Strategies for the MHK Industry: Lessons Learned from Other Industries
The marine and hydrokinetic (MHK) industry plays a vital role in the U.S. clean energy strategy by providing a renewable, domestic energy source that may offset the need for traditional energy sources. The first MHK deployments in the U.S. have incurred very high permitting costs and long timelines for deploying projects, which increases project risk and discourages investment. A key challenge to advancing an economically competitive U.S. MHK industry is reducing the time and cost required for environmental permitting and compliance with government regulations. Other industries such as offshore oil and gas, offshore wind energy, subsea power and data cables, onshore wind energy, and solar energy facilities have all developed more robust permitting and compliance pathways that provide lessons for the MHK industry in the U.S. and may help inform the global consenting process. Based on in-depth review and research into each of the other industries, we describe the environmental permitting pathways, the main environmental concerns and types of monitoring typically associated with them, and factors that appear to have eased environmental permitting and compliance issues.