Jim Beckerle
Research Subjects
Research Interests
Jim Beckerle has a total of 15 co-authors. Here are the top co-authors by number of shared publications:
- Jim Gardner
Senior Project Manager, URS Corp., 1333 Broadway, Oakland, CA 94611
2 shared publications - Wesley Schmutzler
Dept. of Trevi Group, Design, Research & Development, 5819 Via Dismano, 47522 Cesena, Italy
2 shared publications - Alessandro Bertero
Trevi Spa, Design, Research and Development
1 shared publication - Andrew Wilding
Senior Project Manager, URS Corp., 1333 Broadway, Oakland, CA 94611
1 shared publication - Bruce Lelong
Senior Project Manager, USACE, Contractor - Hurricane Protection Office, 7400 Leake Avenue, New Orleans, LA 70160
1 shared publication - David Druss
Senior Project Manager, URS Corp., 1333 Broadway, Oakland, CA 94611
1 shared publication
Latest Publications
- 17 August 2012
- Published by American Society of Civil Engineers (ASCE)
- p. 682-693
Construction Operations and Quality Control of Deep Mixing at Levee LPV111 New Orleans
Deep Mixing (DMM) for the LPV-111 Levee in New Orleans presented many Quality Control and logistical challenges. The project consists of approximately 1.4 million cubic meters (1.7 million cubic yards) of Deep Mixing to a depth of up to 20.5 meters (67 feet), consisting of over 17,000 elements. Eight deep mixing rigs were utilized: three double axis Trevi Turbo Mix rigs (TTM), two single axis TTM rigs, and three double axis CI-CMC rigs. Eight batch plants were used to prepare the grout using over 417,000 tons (460,000 short tons) of slag/cement binder. The work was accomplished within an aggressive schedule by working 24 hours per day, 5.5 days per week. The US Army Corps of Engineers (USACE), using the early contractor involvement (ECI) process, developed a stringent set of specifications in order to ensure a quality product was installed. The drill rigs were equipped with innovative electronic control and logging devices in order to record all pertinent parameters of each element, as well as many other different functions described in this paper. Quality Control of the installation process was continually monitored by examining these records, monitoring the grout produced at each batch plant, and coring over 10,000 linear meters (34,000 feet) of three inch and four inch diameter core. The USACE implemented an extensive Quality Assurance program to monitor the entire deep mixing process, which included independent testing to confirm the Quality Control test results. This paper describes the materials, equipment, methods of construction, and Quality Control procedures that were applied to overcome the tremendous technical and logistical challenges to successfully complete this project.
- 17 August 2012
- Published by American Society of Civil Engineers (ASCE)
- p. 682-693
Construction Operations and Quality Control of Deep Mixing at Levee LPV111 New Orleans
Deep Mixing (DMM) for the LPV-111 Levee in New Orleans presented many Quality Control and logistical challenges. The project consists of approximately 1.4 million cubic meters (1.7 million cubic yards) of Deep Mixing to a depth of up to 20.5 meters (67 feet), consisting of over 17,000 elements. Eight deep mixing rigs were utilized: three double axis Trevi Turbo Mix rigs (TTM), two single axis TTM rigs, and three double axis CI-CMC rigs. Eight batch plants were used to prepare the grout using over 417,000 tons (460,000 short tons) of slag/cement binder. The work was accomplished within an aggressive schedule by working 24 hours per day, 5.5 days per week. The US Army Corps of Engineers (USACE), using the early contractor involvement (ECI) process, developed a stringent set of specifications in order to ensure a quality product was installed. The drill rigs were equipped with innovative electronic control and logging devices in order to record all pertinent parameters of each element, as well as many other different functions described in this paper. Quality Control of the installation process was continually monitored by examining these records, monitoring the grout produced at each batch plant, and coring over 10,000 linear meters (34,000 feet) of three inch and four inch diameter core. The USACE implemented an extensive Quality Assurance program to monitor the entire deep mixing process, which included independent testing to confirm the Quality Control test results. This paper describes the materials, equipment, methods of construction, and Quality Control procedures that were applied to overcome the tremendous technical and logistical challenges to successfully complete this project.
- 17 August 2012
- Published by American Society of Civil Engineers (ASCE)
- p. 661-671
Overview of Deep Mixing at Levee LPV 111, New Orleans, LA
During the storm surge that accompanies a hurricane, New Orleans, Louisiana, is an island and owes its very existence to the 563-km (350-mile) long system of hurricane protection levees and walls that surround the city. The Hurricane and Storm Damage Risk Reduction System (HSDRRS) protects the area from storm surge. An 8.9-km (5.5-mile) long levee section of the Lake Pontchartrain and Vicinity (LPV) Hurricane Protection System, located in East New Orleans and called LPV-111, was designed and constructed by the United States Army Corps of Engineers (USACE) using the latest advances in Deep Mixing Methods (DMM) and innovative contracting and construction procedures. In the process, a new DMM Design Guide was created and peer-reviewed; an innovative contract acquisition plan, Early Contractor Involvement (ECI), was employed; and construction time was minimized through a close relationship among the project owner, designer, and contractor. This is the first in a series of five papers describing the technical and contractual advances and challenges overcome during design and construction. In this paper, an overview of the project is presented and general perspectives from the owner, designer, and contractor are presented.
- 17 August 2012
- Published by American Society of Civil Engineers (ASCE)
- p. 661-671
Overview of Deep Mixing at Levee LPV 111, New Orleans, LA
During the storm surge that accompanies a hurricane, New Orleans, Louisiana, is an island and owes its very existence to the 563-km (350-mile) long system of hurricane protection levees and walls that surround the city. The Hurricane and Storm Damage Risk Reduction System (HSDRRS) protects the area from storm surge. An 8.9-km (5.5-mile) long levee section of the Lake Pontchartrain and Vicinity (LPV) Hurricane Protection System, located in East New Orleans and called LPV-111, was designed and constructed by the United States Army Corps of Engineers (USACE) using the latest advances in Deep Mixing Methods (DMM) and innovative contracting and construction procedures. In the process, a new DMM Design Guide was created and peer-reviewed; an innovative contract acquisition plan, Early Contractor Involvement (ECI), was employed; and construction time was minimized through a close relationship among the project owner, designer, and contractor. This is the first in a series of five papers describing the technical and contractual advances and challenges overcome during design and construction. In this paper, an overview of the project is presented and general perspectives from the owner, designer, and contractor are presented.
- 17 August 2012
- Published by American Society of Civil Engineers (ASCE)
- p. 629-639
Use of Deep Mixing Return Material for Levee Construction
USACE Contract LPV 111 entailed the treatment of 1.3 million cubic meters of soil by the deep mixing method. Approximately 400,000 cubic meters of spoils, termed recycled embankment material (REM) in the LPV 111 contract, would be generated. In lieu of removal of the REM from site, the USACE elected to incorporate the REM in levee construction. Utilization of the REM saved approximately 15M dollars in construction costs. In order to confirm the viability of utilizing REM, a comprehensive field and laboratory testing effort was undertaken. The testing program included multiple test embankments, wherein a range of REM curing ages and compaction variables were tested. Test program results confirmed that REM could be used, while maintaining the performance criteria associated with traditional clay levees.
- 17 August 2012
- Published by American Society of Civil Engineers (ASCE)
- p. 629-639
Use of Deep Mixing Return Material for Levee Construction
USACE Contract LPV 111 entailed the treatment of 1.3 million cubic meters of soil by the deep mixing method. Approximately 400,000 cubic meters of spoils, termed recycled embankment material (REM) in the LPV 111 contract, would be generated. In lieu of removal of the REM from site, the USACE elected to incorporate the REM in levee construction. Utilization of the REM saved approximately 15M dollars in construction costs. In order to confirm the viability of utilizing REM, a comprehensive field and laboratory testing effort was undertaken. The testing program included multiple test embankments, wherein a range of REM curing ages and compaction variables were tested. Test program results confirmed that REM could be used, while maintaining the performance criteria associated with traditional clay levees.