    Stability assessment of railway trackwork scheduling in Sweden

    by Daria Ivina, Zhenliang Ma

    Ensuring the reliability of railway transportation is heavily dependent on the quality of its infrastructure. In this regard, renewal and maintenance of the railway track infrastructure, referred to as trackwork, play a vital role. However, trackwork execution requires temporary capacity restrictions for train traffic. Therefore, harmonising the train and maintenance schedules is critical but challenging to accomplish when one is frequently changing. This paper explores and models the nature of trackwork schedule instability at the tactical level of the scheduling process. We analyse data from one year of trackwork rolling horizon plans, focusing on weekly changes at eight key trackwork locations across Sweden’s railway network. Our study considers various factors that may affect schedule stability, such as track type, location, time of day, train traffic intensity, and the type of prevailing traffic. We find that schedule instability increases as the rolling horizon plan approaches its end. The regression analysis reveals that the most significant predictors of changes in trackwork schedules include previous changes, track type (single vs. double), work location (at station vs. between stations), and the timing of trackwork (daytime vs. nighttime and month). These provide insights to trackwork planners in making informed and proactive decisions about trackwork timeslot allocation.


  • Open Access

    The Downside of Upkeep: Analysing Railway Infrastructure Maintenance Impact on Train Operations in Sweden

    by Daria Ivina, Carl-William Palmqvist

    Efficient and seamless railway operations depend on the systematic and well-coordinated maintenance of both rolling stock and infrastructure. However, track maintenance, or ‘trackwork’, can cause substantial delays if not properly aligned with train schedules. This study comprehensively investigates how trackwork influences train operations in Sweden. It involves an in-depth analysis of an extensive dataset comprising over 225,000 recorded instances of planned trackwork and approximately 32.5 million train passages throughout the year 2017. Multiple logistic and negative binomial regression models showed that train running time delay occurrence is higher in the sections with scheduled trackwork. Trains passing through trackwork are 1.43 times more likely to experience delays compared to trains that do not pass through scheduled trackwork. The likelihood of an opportunity for the train delay recovery passing the section with scheduled trackwork is reduced by 11%. Additionally, the frequency of train delay increase is 16% higher, and delayed recovery is 4% lower in relation to trackwork. With the number of trackwork set to increase over the coming years, these results bring attention to train scheduling and the performance of trackwork.

  • Open Access

    Uncertainties in scheduling and execution of trackwork in Sweden

    by Daria Ivina, Nils O. E. Olsson, Carl-William Palmqvist, Lena Winslott Hiselius

    Trackwork planning and scheduling are demanding because they require strategic foresight and must be completed well in advance. In Sweden, trackwork is performed by maintenance contracting companies during an operation period free from trains. In the contractors’ practice, once the maintenance plan is authorised, some unexpected events might interrupt the plan’s execution, leading to uncertainties. The purpose of this study is to identify and classify uncertainties and strategies applied to manage uncertainties in the contractors’ everyday planning and scheduling of trackwork. This work presents semi-structured interviews with foremen and planners at railway maintenance contracting companies in Sweden. The main findings show that in trackwork planning and scheduling, contractors deal with two types of uncertainties: internal and external. We categorised uncertainties and strategies to deal with uncertainties and described them on tactical and operational levels. The majority of the revealed uncertainties led to trackwork rescheduling. Furthermore, we suggest that current strategies to manage uncertainties applied at contracting companies can be improved by revising organisational design strategies for maintenance projects. This work increases the understanding and supports the management of uncertainties in trackwork planning and scheduling.