    Design and Structural Analysis of the Modular Post-Tensioned Steel Structure for Halls 3, 4 and 6 of Fira de la Gran Vía in Barcelona

    by Ignacio Costales Calvo, Oriol Muntane i Raich, Xavier Gimferrer Vilaplana, Sandra Moliner Nuño

    This article presents the design process and structural analysis for Halls 3, 4, and 6 commissioned by Fira de la Gran Vía in Barcelona. Its objective is to document the complete development of a real structure—from the initial briefing to final execution—highlighting key decisions related to cost, quality, construction speed, and standardization. Rather than simply describing the finished building, the article compares alternative solutions considered at each stage and explains the rationale behind the choices made. Close collaboration between the architectural and structural teams has resulted in a cost-effective solution that has remained relevant twenty-five years after completion. Each structural component is examined in detail, considering its behavior, preliminary sizing, fabrication, transportation, and rapid on-site assembly, all essential under the client’s demanding schedule. It also describes how specific structural details were resolved under project constraints, including instances that required unconventional approaches. Finally, it discusses the role of prestressed longitudinal frames as a strategy for reducing steel consumption. This article underscores the value of integrated architectural and structural thinking in shaping the building from the ground up.

  • Open Access

    Design and Structural Analysis of the Modular Post-Tensioned Steel Structure for Halls 3, 4 and 6 of the Fira de la Gran Vía in Barcelona

    by Ignacio Costales Calvo, Oriol Muntane Raich, Xavier Gimferrer Vilaplana, Sandra Moliner Nuño

    This article presents the design process and subsequent structural analysis for for Halls 3, 4, and 6 of the Fira de la Gran Vía in Barcelona. Close collaboration between the architectural and structural teams resulted in a cost-effective solution that remains relevant twenty-five years after completion. Each structural component is examined in detail, considering its behavior, preliminary sizing, and the rationale behind its fabrication, transportation, and rapid on-site assembly—critical given the client’s tight schedule. This article also describes how structural details were interpreted and realized under the applied stresses and conditions, including instances that required unconventional approaches. Furthermore, the prestressing of the longitudinal frames is presented as a strategy that contributed to reducing the steel structure’s cost during construction. The paper emphasizes the creation of architecture from the ground up, a process often overlooked in the pursuit of a building’s form and function.

  • Open Access

    The Roof of the Glòries Tower: The Design Process for a Steel Dome at a Height of 120 m

    by Ignacio Costales Calvo, Oriol Muntane Raich, Xavier Gimferrer Vilaplana, Pablo Garrido Torres

    Twenty years after its construction, the Agbar Tower remains one of the most recognizable landmarks in Barcelona’s skyline. This article analyzes the dome that serves as its roof. The design of this element required a year of development, during which more than ten iterations were analyzed, resulting in the final design. There was no similar precedent published, as it is a 30 m high dome with significant wind exposure. This study offers an analytical review of the design process and the dome’s enclosure, providing a reference for similar architectural construction projects. This research focuses on describing the elementary loading hypotheses and obtaining numerical models for structural calculations, comparing the results of the five most representative models of the process. Various factors are considered, such as shape, enclosure, structural frequency, deformations obtained, fire protection, and cost. The conclusion focuses on explaining how a form that remains unchanged throughout the process slightly varies the structural solution while respecting the project, to adjust to all the final regulations, construction requirements, cost requirements, and project requirements.

  • Open Access

    Unshoring Process of a Temporary Pillar, in a Seventeen-Storey Building in Sant Adrià del Besós

    by Ignacio Costales Calvo, Jaume Font i Basté, Xavier Gimferrer i Vilaplana, Miquel Llorens Solivera

    In the new construction of a seventeen-storey building, a provisional prop of fourteen-meter height, horizontally braced on two intermediate levels, has been used. Despite the fact that structural logic suggests that it can be cut without having any added safety precautions, the structure of the building, made up of cores and reinforced concrete slabs working spatially, indicates that certain mechanisms be introduced so that, in the event that different and worse behaviors than expected are detected, the process can be stopped and the consequences of the new situation observed can be analyzed. For this purpose, two pairs of four metallic cantilevers were introduced at mid-height with four hydraulic pistons. In addition, the best position of a series of strain gauges as well as transducers were analyzed. At first, a load test was carried out to check that the brackets worked correctly. Once this step was verified, the abutment was cut, and the results were read. The results of stresses and deformations were compared with those expected, always being satisfactory. Finally, four provisional profiles were placed in case after a few days the structure suddenly gave way. The research focuses on obtaining an efficient control system and achieving total security throughout the process, with the comparison of the results strictly necessary for this case. Few resources were used so as not to make the work excessively expensive. We have found important divergences, on the side of security, between calculation and reality. We have also considered that the construction process has an impact on the final results. In the same way, the rigidity of the temporal abutment must be considered before the calculation. All these factors have generated a lower-than-expected deformation in an 8 m cantilever.

  • Open Access

    Unshoring Process of a Temporary Column, in a Seventeen Storey Building in Sant Adrià Del Besós

    by Ignacio Costales Calvo, Jaume Font i Basté, Xavier Gimferrer, Miquel Llorens Solivera

    In a new construction of a seventeen-storey building, it is necessary to remove a prop on the second floor, which has made it possible to complete the structure of the building. In the drafting of the executive project, no security measures were described, because it was understood that they were not necessary. In the construction phase, the need to monitor the process was raised, and to be able to stop it, or reverse it if necessary. It is a reinforced concrete structure, with metal elements and composite elements, with a torsional behavior of the cores making the slabs serve as horizontal diaphragms, so the final behavior could be different from what was expected. To make this process possible, two pairs of four metallic cantilevers were introduced into which four Hydraulic pistons were inserted. Before starting the process, they were loaded to be sure that they would not fail. Strain gauges were also placed to control the stresses and how the situation changed during the unshoring process. The process of cutting the provisional pillar was a success, obtaining less deformations than expected, having a complementary safety.