Shinhyo Kim
Shinhyo Kim has a total of 5 co-authors. Here are the top co-authors by number of shared publications:
- Haram Seo
Department of Naval Architecture and Ocean Systems Engineering, Korea Maritime and Ocean University, Busan 49112, Republic of Korea
1 shared publication - Jaekyeong Lee
Department of Naval Architecture and Ocean Systems Engineering, Korea Maritime and Ocean University, Busan 49112, Republic of Korea
1 shared publication - Jihong Kim
Korea Maritime Transportation Safety Authority (KOMSA), Sejong 30100, Republic of Korea
1 shared publication - Kyeongho Kim
Department of Naval Architecture and Ocean Systems Engineering, Korea Maritime and Ocean University, Busan 49112, Republic of Korea
1 shared publication - Minjoo Choi
Department of Naval Architecture and Ocean Systems Engineering, Korea Maritime and Ocean University, Busan 49112, Republic of Korea
1 shared publication
Latest Publications
- Open Access
- 24 January 2025
- Published by MDPI AG in Journal of Marine Science and Engineering
- Vol. 13 (2) , 222
A Mixed Integer Linear Programming Model for Rapid Rescheduling in Ship and Offshore Unit Design Projects
Shipbuilding and offshore projects frequently require schedule adjustments due to unforeseen factors such as material supply delays, technical issues, and adverse weather conditions. These adjustments are often managed manually, resulting in significant time consumption and an increased risk of human error. Unlike production scheduling, little attention has been given to design scheduling, particularly in the context of rescheduling. To address this gap, this paper presents an optimization model that automates the rescheduling process for shipbuilding and offshore unit design projects. The model generates updated schedules that accommodate necessary changes while minimizing deviations from the initial schedule. In a real-world case involving 857 tasks, the model generated a schedule in under one second, preserving approximately 80% of the original schedule and achieving a 20% improvement in adherence compared to the original scheduling method. Furthermore, the model demonstrated exceptional scalability by efficiently generating optimized schedules for 108,700 tasks in under three minutes. These results demonstrate the model’s capability to provide rapid, efficient, and scalable rescheduling solutions, enabling quick and iterative refinement processes.
- 24 January 2025
- Published by MDPI AG in Journal of Marine Science and Engineering
- Vol. 13 (2) , 222
Open AccessA Mixed Integer Linear Programming Model for Rapid Rescheduling in Ship and Offshore Unit Design Projects
Shipbuilding and offshore projects frequently require schedule adjustments due to unforeseen factors such as material supply delays, technical issues, and adverse weather conditions. These adjustments are often managed manually, resulting in significant time consumption and an increased risk of human error. Unlike production scheduling, little attention has been given to design scheduling, particularly in the context of rescheduling. To address this gap, this paper presents an optimization model that automates the rescheduling process for shipbuilding and offshore unit design projects. The model generates updated schedules that accommodate necessary changes while minimizing deviations from the initial schedule. In a real-world case involving 857 tasks, the model generated a schedule in under one second, preserving approximately 80% of the original schedule and achieving a 20% improvement in adherence compared to the original scheduling method. Furthermore, the model demonstrated exceptional scalability by efficiently generating optimized schedules for 108,700 tasks in under three minutes. These results demonstrate the model’s capability to provide rapid, efficient, and scalable rescheduling solutions, enabling quick and iterative refinement processes.