Earned Duration Management Control Charts: Role of Control Limit Width Definition for Construction Project Duration Monitoring
- 1 September 2021
- journal article
- research article
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 147 (9) , 04021108
Abstract
The design of control charts refers to the selection of the sample, the sampling interval, and the width of the control limits. The literature on the use of control charts for project monitoring is concerned mainly with the first two parameters, and does not dedicate enough attention to how to determine the width of the control limits. This paper highlighted the relevant role that the appropriate definition of probabilistic control limit width plays in the project control and the performance of the control charts used to monitor the duration of construction projects. The main contribution is the proposal of a two-step simulation approach to set the most appropriate control limit width. The application of the proposed method was presented. Results demonstrated that there is a trade-off between the performance of the control charts and the control effort to investigate the cause of every warning signal. The preferable choice of is influenced strongly by different project duration targets, risk and uncertainty scenarios estimated in the planning phase, and the team’s risk profile.
Keywords
This publication has 35 references indexed in Scilit:
- Monitoring project duration and cost in a construction project by applying statistical quality control chartsInternational Journal of Project Management, 2013
- On the dynamic use of project performance and schedule risk information during projecttrackingOmega, 2011
- An extension of the EVM analysis for project monitoring: The Cost Control Index and the Schedule Control IndexInternational Journal of Project Management, 2011
- Prediction of project outcomeInternational Journal of Project Management, 2009
- Project Performance Evaluation Based on Statistical Process Control TechniquesJournal of Construction Engineering and Management, 2008
- A comparison of different project duration forecasting methods using earned value metricsInternational Journal of Project Management, 2006
- Managing uncertainty in major equipment procurement in engineering projectsEuropean Journal of Operational Research, 2006
- On Small Shifts in Quality ControlQuality Engineering, 2003
- Integrating supply chain and critical chain concepts in engineer-procure-construct (EPC) projectsInternational Journal of Project Management, 2002
- Economic design ofX¯ control charts for two manufacturing process modelsNaval Research Logistics Quarterly, 1985