A Systematic Method to Analyze Force Majeure in Construction Claims
Open Access
Abstract
In construction delay claims, force majeure is normally recognized as an excusable risk that entitles contractors only to time extensions, but neither of the contracting parties is entitled to monetary compensation to recover delay damages. However, there are instances where contractors are entitled to both time and cost compensations, as evidenced by some court cases relating to force majeure claims. Such instances involve attributing the occurrence of the force majeure to the effect of other prior delay events that pushed project performance into the period of the force majeure. Existing delay analysis methods are not capable of addressing this issue, as none take the impact of other delays into consideration when analyzing force majeure claims. Stimulated by this gap, this study proposes an improved and sound method for fairly analyzing the responsibility of force majeure delay claims amongst contracting parties. This method was implemented on a case project to help demonstrate its application and also ascertain its practicability. The contribution of this paper is twofold. First, it has highlighted the situation of force majeure delay that can be compensable, creating more awareness among researchers and industry practitioners. The second is a proposed systematic process to appropriately analyze its responsibility, which equitably addresses claims from such delays with little or no chance of dispute ensuing.Keywords
This publication has 33 references indexed in Scilit:
- Approaches to Delay Claims Assessment Employed in the UK Construction IndustryBuildings, 2013
- Assessment of climate change adaptation costs for the U.S. road networkGlobal Environmental Change, 2013
- Construction Delay Analysis Techniques—A Review of Application Issues and Improvement NeedsBuildings, 2013
- Critical path effect based delay analysis method for construction projectsInternational Journal of Project Management, 2012
- Causes of delay in large construction projectsInternational Journal of Project Management, 2006
- Avoiding and Minimizing Construction Delay Claim Disputes in Relational ContractingJournal of Professional Issues in Engineering Education and Practice, 2006
- Improving existing delay analysis techniques for the establishment of delay liabilitiesConstruction Innovation, 2004
- Construction delay analysis techniquesConstruction Management and Economics, 1996
- Construction contractor's claims analysis: An integrated system approachBuilding Research & Information, 1991
- Reasons for delays in public projects in TurkeyConstruction Management and Economics, 1985