Total float management: computerized technique for construction delay analysis
Authors:
- 1 May 2016
- journal article
- Published by Canadian Science Publishing in Canadian Journal of Civil Engineering
- Vol. 43 (5) , 391-401
Abstract
Developing a holistic and accurate delay analysis software is still challenging the current delay analysis practices. Most of the existing delay analysis techniques are not programmed and still depend on manual calculations. The currently available computerized delay analysis techniques are still limited, suffer from many drawbacks, and do not consider many of the delay analysis situations. This paper introduces web-based software called total float management (TFM) software for analyzing delay claim utilizing TFM delay analysis technique. The TFM technique depends on day-by-day analysis, which gives more accurate analysis over other techniques. The software has the ability to import schedule data from Primavera P6 and Microsoft Project (MS project) software in various formats. This feature makes analysis easier and reduces the time required for data input. Many other features are included in the TFM software, such as the ability to address concurrent delays, change orders, and acceleration events.Keywords
This publication has 21 references indexed in Scilit:
- Critical path effect based delay analysis method for construction projectsInternational Journal of Project Management, 2012
- Critical Path Segments Scheduling TechniqueJournal of Construction Engineering and Management, 2010
- Review of Delay Analysis Methods: A Process-Based ComparisonThe Open Construction & Building Technology Journal, 2009
- Delays in construction projects: The case of JordanInternational Journal of Project Management, 2008
- An integrated decision support system for dealing with time extension entitlementsAutomation in Construction, 2008
- Developments in the Analysis of Extensions of TimeJournal of Professional Issues in Engineering Education and Practice, 2007
- Causes and effects of delays in Malaysian construction industryInternational Journal of Project Management, 2007
- Causes of delay in large construction projectsInternational Journal of Project Management, 2006
- The applicability of project management software and advanced IT techniques in construction delays mitigationInternational Journal of Project Management, 1997
- Total Float Traded as CommodityJournal of Construction Engineering and Management, 1991