Numerical Simulation of Interlevel Pillar Response During Underground Gold Ore Mining: The Akbakay Deposit Case
Open Access
- 15 September 2026
- journal article
- research article
- Published by MDPI AG in Geosciences
- Vol. 16 (9) , 374
Abstract
Designing interlevel pillars for deep, structurally complex vein deposits requires balancing rock mass stability against ore recovery. This study evaluates the geomechanical response of the Kenzhem area of the Akbakay gold deposit using a three-dimensional finite-element model that reproduces the lithological structure, irregular ore-body geometry, underground workings, and mined-out stopes. Four extraction scenarios were analyzed: complete extraction without pillars and mining with 10, 15, and 20 m inter-stope pillars. Stability was assessed using maximum total displacement, the extent and connectivity of yielded zones predicted by the generalized Hoek–Brown criterion, and numerical convergence. Pillarless extraction produced displacements of 2.6–3.0 m, a continuous yielded zone extending toward the surface, and loss of numerical convergence. A 10 m pillar reduced displacements to 0.50–0.66 m but did not provide a stable equilibrium state. Increasing the pillar thickness to 15 m reduced the maximum displacement to approximately 0.08 m, localized the yielded zones near excavation boundaries, and ensured convergence. A 20 m pillar produced only a minor additional reduction to 0.065–0.070 m without materially changing the failure pattern. Therefore, a 15 m inter-stope pillar provides the most rational balance between geomechanical safety and ore recovery under the investigated conditions.Keywords
All Related Versions
Funding Information
- Committee of Science of the Ministry of Science and Higher Education of the Republic of Kazakhstan (AP26198535)
This publication has 46 references indexed in Scilit:
- Research on Optimization of Stope Structural Parameters for Open-Pit to Underground Mining Transition Based on Mathews Stability Graph Method2026
- Microscale damage evolution of high-temperature granite under liquid nitrogen thermal shock based on computed tomography analysisEngineering Geology, 2025
- AI-Powered Geotechnics: Enhancing Rock Mass Classification for Safer Engineering PracticesRock Mechanics and Rock Engineering, 2024
- A review of multiscale numerical modeling of rock mechanics and rock engineeringDeep Underground Science and Engineering, 2024
- A review on the geotechnical design and optimisation of ultra-long ore passes for deep mass miningEnvironmental Earth Sciences, 2024
- The Consolidated Mathews Stability Graph for Open Stope DesignGeotechnical and Geological Engineering, 2022
- Numerical Simulation of Crown Pillar Behaviour in Transition from Open Pit to Underground MiningGeotechnical and Geological Engineering, 2021
- Failure and mechanical behavior of transversely isotropic rock under compression-shear tests: Laboratory testing and numerical simulationEngineering Fracture Mechanics, 2021
- Investigation of Rock Mass Stability Around the Tunnels in an Underground Mine in USA Using Three-Dimensional Numerical ModelingRock Mechanics and Rock Engineering, 2017
- Rock bolt supporting factor: rock bolting capability of rock massBulletin of Engineering Geology and the Environment, 2015