A Two-Layer Approach for the Decentralized Multi-Project Scheduling Problem Sharing Multi-Skilled Staff
Open Access
- 23 February 2024
- journal article
- research article
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Access
- Vol. 12, 29204-29221
Abstract
With the rapid development of economic globalization and information technology, the projects undertaken by enterprises are gradually becoming larger and more complex. The multi-project management model has become the norm in enterprise management, and it shows a trend of decentralization in terms of geographical distribution and management environment. This decentralization mainly manifests in the fact that each project has its own private information and benefit objectives and shares limited global resources with other projects during the execution process, forming a decentralized decision-making environment. As an extension of the resource-constrained project scheduling problem (RCPSP), the decentralized resource-constrained multi-project scheduling problem (DRCMPSP) is a project scheduling problem that integrates single project scheduling and global resource coordination allocation in a decentralized decision-making environment with multiple independent decision-makers. Furthermore, when considering global resources as multi-skilled staff, the decentralized resource-constrained multi-project scheduling problem sharing multi-skilled staff (DRCMPSP-MS) studied in this paper is proposed. A two-layer model containing local scheduling and global coordination decision-making is established to describe this problem. To solve this problem, a two-layer approach (TLA) is proposed. In the local scheduling layer, a bat algorithm based on forward-backward scheduling (BAFBS) is developed to generate local baseline schedules to minimize the single-project completion time. In the global coordination decision-making layer, a variable neighborhood tabu search algorithm with greedy assignment strategy (VNTS-GAS) is designed to resolve global resource conflicts to minimize the multi-project total tardiness cost. Computational experiments are conducted based on the Multi-Project Scheduling Problem LIBrary (MPSPLIB) dataset. The results show that the BAFBS can obtain high-quality local baseline schedules. Compared to the existing decentralized and centralized methods, our proposed TLA can obtain better solutions on most problem subsets, which proves that our approach can effectively coordinate the allocation of multi-skilled staff among multiple projects.Keywords
Funding Information
- National Natural Science Foundation of China (72271012)
This publication has 65 references indexed in Scilit:
- A sealed bid auction-based two-stage approach for a decentralized multiproject scheduling problem with resource transfersApplied Intelligence, 2022
- Multi-skill resource constrained project scheduling using a multi-objective discrete Jaya algorithmApplied Intelligence, 2021
- P-GWO and MOFA: two new algorithms for the MSRCPSP with the deterioration effect and financial constraints (case study of a gas treating company)Applied Intelligence, 2020
- A generic heuristic for multi-project scheduling problems with global and local resource constraints (RCMPSP)Soft Computing, 2018
- A multi-unit combinatorial auction based approach for decentralized multi-project schedulingAutonomous Agents and Multi-Agent Systems, 2017
- Parallel bat algorithm for optimizing makespan in job shop scheduling problemsJournal of Intelligent Manufacturing, 2015
- Hybrid ant colony optimization in solving multi-skill resource-constrained project scheduling problemSoft Computing, 2014
- An efficient metaheuristic for integrated scheduling and staffing IT projects based on a generalized minimum cost flow networkNaval Research Logistics (NRL), 2012
- RESCON: Educational project scheduling softwareComputer Applications in Engineering Education, 2011
- A market-based multi-agent system model for decentralized multi-project schedulingAnnals of Operations Research, 2006