Financial optimisation of the scheduling for the multi-stage project
Authors:
Open Access
- 1 December 2017
- journal article
- research article
- Published by Walter de Gruyter GmbH in Bulletin Of The Polish Academy Of Sciences-Technical Sciences
- Vol. 65 (6) , 899-908
Abstract
The paper analyses the problem of discounted cash flow maximising for the resource-constrained project scheduling from the project contractor’s perspective. Financial optimisation for the multi-stage project is considered. Cash outflows are the contactor’s expenses related to activity execution. Cash inflows are the client’s payments for the completed milestones. To solve the problem, the procedure of backward scheduling taking into account contractual milestones is proposed. The effectiveness of this procedure, as used to generate solutions for the simulated annealing algorithm, is verified with use of standard test instances with additionally defined cash flows and contractual milestones.Keywords
This publication has 31 references indexed in Scilit:
- Resource constrained project scheduling problem with discounted earliness–tardiness penalties: Mathematical modeling and solving procedureComputers & Industrial Engineering, 2013
- An efficient multi-pass heuristic for project scheduling with constrained resourcesInternational Journal of Production Research, 2003
- On modelling payments in projectsJournal of the Operational Research Society, 1997
- Project network models with discounted cash flows a guided tour through recent developmentsEuropean Journal of Operational Research, 1997
- Using discounted cash flow heuristics to improve project net present valveJournal of Operations Management, 1996
- The development of cash flow weight procedures for maximizing the net present value of a projectJournal of Operations Management, 1996
- Heuristic scheduling of capital constrained projectsJournal of Operations Management, 1996
- Serial and parallel resource-constrained project scheduling methods revisited: Theory and computationEuropean Journal of Operational Research, 1996
- An iterative scheduling technique for resource-constrained project schedulingEuropean Journal of Operational Research, 1992
- Some Properties of Schedules for Large Projects with Limited ResourcesOperations Research, 1964