Abstract
One of the most challenging tasks of a construction project planner is to simultaneously minimize the total project cost and total project duration while considering issues related to optimal resource allocation and resource leveling. Therefore, project planners face complicated multivariate, time-cost-resource optimization (TCRO) problems that require time-cost-resource tradeoff analysis. The hybrid GA–PSO approach is presented to solve complex, TCRO problems in construction project planning. The proposed approach uses the fuzzy set theory to characterize uncertainty about the input data (i.e., time, cost, and resources required to perform an activity) in this hybrid approach. The proposed fuzzy-enabled hybrid GA–PSO approach is applied to solve two optimization problems that are found in the construction project planning literature. It is shown that the proposed fuzzy enabled hybrid GA–PSO approach is superior to existing optimization algorithms at finding better project schedule solutions with ...