Operating reserve scheduling for island systems with parallel AC-DC interconnectors: The case of Crete
- 1 June 2017
- conference paper
- Published by Institute of Electrical and Electronics Engineers (IEEE)
- Vol. 21, 1-5
Abstract
In this paper, a unit commitment model is presented for island systems connected to the mainland through parallel ac and dc interconnectors. The main goal is to determine the hourly economic dispatch of all generating units, leading to maximum penetration of renewables and minimization of total operating costs. The analysis is performed in GAMS using the Mixed Integer Linear Programming (MILP) method, where all essential constraints, such as the required operating reserves, transmission capacity constraints and technical limits of the generating units and interconnectors, are properly accounted for. Crete is selected as the study-case system, whose interconnection to the Greek mainland is currently being planned with parallel ac and dc links.Keywords
This publication has 6 references indexed in Scilit:
- Evaluation of control schemes for island VSC-HVDC links operating in parallel with AC interconnectors2017
- Operation of the electrical system of Crete in interconnection with the mainland grid: A stability study2013
- Co-Optimization of Generation Unit Commitment and Transmission Switching With N-1 ReliabilityIEEE Transactions on Power Systems, 2010
- A Computationally Efficient Mixed-Integer Linear Formulation for the Thermal Unit Commitment ProblemIEEE Transactions on Power Systems, 2006
- Optimal response of a power generator to energy, AGC, and reserve pool-based marketsIEEE Transactions on Power Systems, 2002
- Optimal response of a thermal unit to an electricity spot marketIEEE Transactions on Power Systems, 2000