Two-machine flow-shop scheduling to minimize total late work
Authors:
- 1 June 2006
- journal article
- research article
- Published by Taylor & Francis in Engineering Optimization
- Vol. 38 (4) , 501-509
Abstract
This article considers a two-machine flow-shop scheduling problem of minimizing total late work. Unlike tardiness, which is based upon the difference between the job completion time and the due date, the late work of a job is defined as the amount of work not completed by its due date. This article first shows that the problem remains non-deterministic polynomial time (NP) hard even if all jobs share a common due date. A lower bound and a dominance property are developed to design branch-and-bound algorithms. Computational experiments are conducted to assess the performance of the proposed algorithms. Numerical results demonstrate that the lower bound and dominance rule can help to reduce the computational efforts required by exploring the enumeration tree. The average deviation between the solution found by tabu search and the proposed lower bound is less than 3%, suggesting that the proposed lower bound is close to the optimal solution.Keywords
This publication has 9 references indexed in Scilit:
- The two-machine flow-shop problem with weighted late work criterion and common due dateEuropean Journal of Operational Research, 2005
- Open shop scheduling problems with late work criteriaDiscrete Applied Mathematics, 2004
- Single machine scheduling to minimize total weighted late work: a comparison of scheduling rules and search algorithmsComputers & Industrial Engineering, 2002
- Single Machine Scheduling to Minimize Total Weighted Late WorkINFORMS Journal on Computing, 1995
- Single Machine Scheduling to Minimize Total Late WorkOperations Research, 1992
- Approximation algorithms for scheduling a single machine to minimize total late workOperations Research Letters, 1992
- Minimizing mean weighted execution time loss on identical and uniform processorsInformation Processing Letters, 1987
- Optimization and Approximation in Deterministic Sequencing and Scheduling: a Survey1979
- Optimal two‐ and three‐stage production schedules with setup times includedNaval Research Logistics Quarterly, 1954