From conventional to mechanised tunnelling – A technical and operational challenge
Author:
- 5 December 2018
- journal article
- topics
- Published by Wiley in Geomechanics and Tunnelling
- Vol. 11 (6) , 636-646
Abstract
The article provides a summarised report about the redesign of the 8,822 m long Boßler Tunnel from the originally intended shotcrete method to a mechanically driven tunnel. The twin‐bore Boßler Tunnel is the main contract on the Albaufstieg (Alb ascent) section of the new DB line from Wendlingen to Ulm as part of the major DB project Stuttgart–Ulm. In 2012, the tunnel was tendered by the DB AG for construction by conventional methods with shotcrete support, but a bid for the Boßler Tunnel was received from the consortium Porr, Hinteregger, Östu/Stettin and Swietelsky with an alternative proposal to drive a 2,900 m long section of the tunnel with a machine. The contract was awarded with the alternative proposal and during the construction of the Boßler Tunnel, a change was then made to complete mechanised tunnelling in a unique technical and operational process. The report provides an insight into the challenges of a change to the overall construction system, undertaken after the award during the construction period, for the driving of altogether 17,500 m of tunnel bores. Construction operations, logistics, design for construction, additional investigation measures and contractual parameters were reorganised and redesigned on a tight schedule. Starting with the original 5,800 m TBM drive and the start of tunnelling in April 2015, the entire Boßler Tunnel was actually constructed as a mechanically driven single‐pass tunnel by June 2018.Keywords
This publication has 2 references indexed in Scilit:
- Optimisation of the TBM drive at the Boßler Tunnel using the observation method and an incremental design and contract development processGeomechanics and Tunnelling, 2017
- Why were 800 m of the Boßler Tunnel built twice? - TBM passing a shotcrete sectionGeomechanics and Tunnelling, 2017