Scheduling Construction Projects Using Evolutionary Algorithm
- 1 August 2006
- journal article
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 132 (8) , 861-870
Abstract
This paper attempts to use evolutionary algorithms to solve the problem of minimizing construction project duration in deterministic conditions, with in-time changeable and limited accessibility of renewable resources (workforce, machines, and equipment). Particular construction processes (with various levels of complexity) must be conducted in the established technological order and can be executed with different technological and organizational variants (different contractors, technologies, and ways of using resources). Such a description of realization conditions allows the method to also be applied to solving more complex problems that occur in construction practice (e.g., scheduling resources for a whole company, not only for a single project). The method’s versatility distinguishes it from other approaches presented in numerous publications. To assess the solutions generated by the evolutionary algorithm, the writers worked a heuristic algorithm (for the allocation of resources and the calculation of the shortest project duration). The results obtained by means of this methodology seem to be similar to outcomes of other comparable methodologies. The proposed methodology (the model and the computer system) may be of great significance to the construction industry. The paper contains some examples of the practical use of the evolutionary algorithm for project planning with time constraints.Keywords
This publication has 18 references indexed in Scilit:
- A branch-and-bound algorithm for the resource-constrained project scheduling problemMathematical Methods of Operations Research, 2000
- GA-Based Multicriteria Optimal Model for Construction SchedulingJournal of Construction Engineering and Management, 1999
- Optimization of Resource Allocation and Leveling Using Genetic AlgorithmsJournal of Construction Engineering and Management, 1999
- Genetic Algorithms Application and Testing for Equipment SelectionJournal of Construction Engineering and Management, 1999
- Resource-constrained project scheduling: Notation, classification, models, and methodsEuropean Journal of Operational Research, 1999
- Scheduling/Cost Optimization and Neural Dynamics Model for ConstructionJournal of Construction Engineering and Management, 1997
- Network‐based project planning and schedulingIndustrial Management & Data Systems, 1996
- Genetic Algorithms in Discrete Optimization of Steel Truss RoofsJournal of Computing in Civil Engineering, 1994
- Optimal sizing, geometrical and topological design using a genetic algorithmStructural and Multidisciplinary Optimization, 1993
- Expert systems in production schedulingEuropean Journal of Operational Research, 1987