Sustainable workforce scheduling in construction program management
- 1 August 2013
- journal article
- research article
- Published by Taylor & Francis in Journal of the Operational Research Society
- Vol. 64 (8) , 1169-1181
Abstract
The multimode resource-constrained project scheduling problem (MRCPSP) deals with the scheduling of a set of projects with alternative requirements of renewable and non-renewable resources. Solutions to the MRCPSP usually consider objectives in terms of cost and time. However, social objectives related with the workforce may impact the performance of projects and affect program sustainability goals. To account for this new social input, this paper extends the MRCPSP and proposes a new multiobjective mixed-integer programming model. The proposed solution method uses an a priori lexicographic ordering of the objectives, followed by an ɛ-constraints approach. The model is illustrated with a case study of a construction program.Keywords
This publication has 31 references indexed in Scilit:
- Augmented heuristic algorithm for multi-skilled resource schedulingAutomation in Construction, 2011
- A methodology to identify sustainability indicators in construction project management—Application to infrastructure projects in SpainEcological Indicators, 2010
- Optimizing the utilization of multiple labor shifts in construction projectsAutomation in Construction, 2010
- Optimal Assignment of Multiskilled Labor in Building Construction ProjectsInternational Journal of Construction Education and Research, 2010
- Development of composite sustainability performance index for steel industryEcological Indicators, 2007
- Solution methods for the bi-objective (cost-coverage) unconstrained facility location problem with an illustrative exampleAnnals of Operations Research, 2006
- Multimode Project Scheduling Based on Particle Swarm OptimizationComputer-Aided Civil and Infrastructure Engineering, 2006
- Disruption management for resource-constrained project schedulingJournal of the Operational Research Society, 2005
- Key performance indicators for infrastructure sustainability – a comparative study between Hong Kong and South AfricaJournal of Engineering, Design and Technology, 2005
- Resource Constrained Scheduling within Fixed Project DurationsJournal of the Operational Research Society, 1993