Blockchain-Integrated PROMETHEE Framework for Legal Risk Prioritization in High Speed–Rail Project Construction Disputes: A Case Study
- 1 November 2026
- journal article
- Published by American Society of Civil Engineers (ASCE) in Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
- Vol. 18 (4)
Abstract
Construction disputes in large infrastructure projects often stem from inadequately defined contractual obligations, misaligned risk allocation, and technical uncertainties. In high-speed rail (HSR) developments, these issues are exacerbated by the scale, complexity, and multiplicity of stakeholders involved. This study investigates the prioritization of key performance indicators (KPIs) associated with construction disputes in the Mumbai–Ahmedabad high-speed rail (MAHSR) project, India’s flagship bullet train initiative. Using expert input from 54 professionals across legal, engineering, and project management domains, the preference ranking organization method for enrichment evaluation (PROMETHEE) multicriteria decision-making method was applied to rank legal, contractual, and technical risks contributing to disputes. The most critical factors identified include ambiguous risk allocation clauses, design errors, building information modeling (BIM) clashes, noncompliance with environmental regulations, geotechnical data mismanagement, and delayed contractor payments. A sensitivity analysis confirms the robustness of these findings across different weighting scenarios. The study also explores the potential of blockchain-enabled smart contracts to enhance transparency, automate compliance, and improve dispute resolution processes. The findings provide actionable insights for legal professionals, project managers, and policymakers involved in HSR and similar large infrastructure projects, emphasizing the need for meticulous contract drafting, proactive risk allocation, and strategic integration of digital technologies. The research contributes to the theoretical understanding of risk allocation and dispute causation, while offering practical insights for fostering more resilient and collaborative project environments.Keywords
This publication has 23 references indexed in Scilit:
- Application of Factor Analysis and Structure Equation Modelling for Evaluation of Key Performance Indicators for Development of Sustainable Transportation InfrastructureJournal of The Institution of Engineers (India): Series A, 2023
- A framework for smart construction contracts using BIM and blockchainScientific Reports, 2023
- Research on the risk of Metro PPP projects based on DEMATEL-ANPE3S Web of Conferences, 2023
- A decentralized structure to reduce and resolve construction disputes in a hybrid blockchain networkAutomation in Construction, 2022
- Evaluation of Key Performance Indicators of Integrated Project Delivery and BIM Model for Infrastructure Transportation Project in Ahmedabad, India through Decision-Making ApproachJournal of The Institution of Engineers (India): Series A, 2021
- Application of integrated fuzzy FCM-BIM-IoT for sustainable material selection and energy management of metro rail station box project in western IndiaInnovative Infrastructure Solutions, 2021
- Blockchain in the built environment and construction industry: A systematic review, conceptual models and practical use casesAutomation in Construction, 2019
- Comparative Study of Risk Indices for Infrastructure Transportation Project Using Different MethodsJournal of The Institution of Engineers (India): Series A, 2019
- What you Should Know about Megaprojects and Why: An OverviewProject Management Journal, 2014
- Causes and effects of delays in Malaysian construction industryInternational Journal of Project Management, 2007