Building an infrastructure project performance in the North-West Province Department of Public Works and Roads
Authors:
- Davison MurwiraDMDavison Murwira
- Michiel BekkerMBMichiel Bekker
Open Access
- 30 November 2017
- journal article
- research article
- Published by University of the Free State in Acta Structilia 23(2)
- Vol. 24 (2) , 128-145
Abstract
Building and infrastructure projects at the North-West Province Department of Public Works and Roads (NW DPWR) often perform poorly in terms of overrunning both the original approved timeline and the budget. Adding to poor time and cost performances, these projects often do not meet the desired functional requirements. This article reports on findings of a study which investigated the causes of these poor performances in the NW DPWR. Fifty potential causes of poor performance were identified from literature. These factors were grouped under three main related categories of owner-related, contractor-related and consultant-related and were subjected to a questionnaire survey to identify the most critical causes of failure. The results were analysed using the Relative Importance Index (RII) and Spearman’s Rank Correlation Coefficients. The results indicated that the most significant causes of poor building and infrastructure project performance in the NW DPWR include underestimation of project cost, the lack of experience in executing projects, contractor’s cash-flow constraints, corruption and bribery during the bidding and contract award phase, as well as poor site management and supervision. Recommendations are made to prevent similar causes of projects failure in the NW DPWR in future.Keywords
This publication has 73 references indexed in Scilit:
- Causes and Effects of Delays and Disruptions in Construction Projects in TanzaniaAustralasian Journal of Construction Economics and Building - Conference Series, 2013
- Delays in Building Construction Projects in GhanaConstruction Economics and Building, 2010
- Cost escalation and schedule delays in road construction projects in ZambiaInternational Journal of Project Management, 2009
- Collaborative relationships in construction: the UK contractors' perceptionEngineering, Construction and Architectural Management, 2007
- Construction Delays and Their Causative Factors in NigeriaJournal of Construction Engineering and Management, 2006
- Causes of delay in large construction projectsInternational Journal of Project Management, 2006
- Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case studyInternational Journal of Project Management, 2003
- Construction delay: a quantitative analysisInternational Journal of Project Management, 2000
- A comparative study of causes of time overruns in Hong Kong construction projectsInternational Journal of Project Management, 1997
- Reasons for overrun in public sector construction projects in NigeriaInternational Journal of Project Management, 1990