Stochastic Construction Time-Cost Trade-Off Analysis
Authors:
- 1 April 2000
- journal article
- research article
- Published by American Society of Civil Engineers (ASCE) in Journal of Computing in Civil Engineering
- Vol. 14 (2) , 117-126
Abstract
Traditional time-cost trade-off analysis assumes that the time and cost of an option within an activity are deterministic. However, in reality the time and cost are uncertain. Therefore, in analyzing the time-cost trade-off problem, uncertainties should be considered when minimizing project duration or cost. Simulation techniques are useful for analyzing stochastic effects, but a general strategy/algorithm is needed to guide the analysis to obtain optimal solutions. This paper presents a hybrid approach that combines simulation techniques and genetic algorithms to solve the time-cost trade-off problem under uncertainty. The results show that genetic algorithms can be integrated with simulation techniques to provide an efficient and practical means of obtaining optimal project schedules while assessing the associated risks in terms of time and cost of a construction project. This new approach provides construction engineers with a new way of analyzing construction time/cost decisions in a more realistic manner. Historical time/cost data and available options to complete a project can be modeled, so that construction engineers can identify the best strategies to take to complete the project at minimum time and cost. Also, what-if scenarios can be explored to decide the desired/optimal time and/or cost in planning and executing project activities.Keywords
This publication has 18 references indexed in Scilit:
- Using Genetic Algorithms to Solve Construction Time-Cost Trade-Off ProblemsJournal of Computing in Civil Engineering, 1997
- The LP/IP hybrid method for construction time-cost trade-off analysisConstruction Management and Economics, 1996
- The discrete time-cost tradeoff problem revisitedEuropean Journal of Operational Research, 1995
- Resource allocation for a stochastic CPM-type network through perturbation analysisEuropean Journal of Operational Research, 1994
- Heuristics for scheduling projects with resource restrictions and several resource-duration modesInternational Journal of Production Research, 1993
- Schedule compression using the direct stiffness methodCanadian Journal of Civil Engineering, 1993
- Resource allocation via dynamic programming in activity networksEuropean Journal of Operational Research, 1993
- A new approach for project scheduling with a limited resourceInternational Journal of Production Research, 1991
- A comparison between the VERT program and other methods of project duration estimationOmega, 1987
- Stochastic Bounds on Distributions of Optimal Value Functions with Applications to PERT, Network Flows and ReliabilityOperations Research, 1986