Simulation-Based Scheduling of Modular Construction Using Multi-agent Resource Allocation
Authors:
- Hosein TaghaddosHTHosein Taghaddos
- Ulrich HermannUHUlrich Hermann
- Simaan AbouRizkSASimaan AbouRizk
- Yasser MohamedYMYasser Mohamed
- 1 August 2010
- conference paper
- Published by Institute of Electrical and Electronics Engineers (IEEE)
- p. 115-120
Abstract
Modular construction is common practice for building industrial plants in the Alberta oil sands region, Canada because of the savings in cost and schedule, and improving safety and quality. Each module represents a unique construction project. Thus, modular construction is considered as multi-project construction. Scheduling and effective allocation of resources (e.g., space, skilled crew, construction equipment) in such large-scale construction projects is a challenging process. The production schedule is expected to satisfy numerous uncertain factors and constraints posed by the site layout, resource limitations, the construction process, and various supply chains (e.g., spool fabrication shop). Traditional network-based scheduling approaches are ineffective in scheduling the multi-project environment of modular construction and optimum allocation of resources. This paper presents a hybrid approach based on discrete event simulation modeling and Multi-Agent Resource Allocation (MARA) for scheduling modular construction. Modules represent agents who bid for resources (e.g., space in the yard) to maximize their individual welfare. An auctioneer is also designed who allocates the available resources to the bidding agents by maximizing the overall welfare of the society of agents. The auctioneer can employ various combinatorial optimization algorithms (greedy and ascending-auction algorithms in this study) to allocate the resources to the agents. Auctions are held regularly until the end of the simulation model to allocate the resources among agents. This paper also presents the successful implementation of this approach in an actual case study of a module assembly yard.Keywords
This publication has 7 references indexed in Scilit:
- Integrated Simulation-Based Scheduling for Module Assembly Yard2009
- A framework for simulating industrial construction processes2008
- S4HARA: System for HIV/AIDS resource allocationCost Effectiveness and Resource Allocation, 2008
- Simulation‐based scheduling of module assembly yards: case studyEngineering, Construction and Architectural Management, 2007
- Optimal construction project planning2003
- GA-Based Multicriteria Optimal Model for Construction SchedulingJournal of Construction Engineering and Management, 1999
- Pull-Driven Scheduling for Pipe-Spool Installation: Simulation of Lean Construction TechniqueJournal of Construction Engineering and Management, 1998