Generation schemes for the resource-constrained project scheduling problem with partially renewable resources and generalized precedence constraints
Open Access
- 17 January 2024
- journal article
- research article
- Published by Springer Nature in Annals of Operations Research
- Vol. 338 (1) , 173-192
Abstract
In recent years, new resource types have been established in project scheduling. These include so-called partially renewable resources, whose total capacity applies only to a subset of periods in the planning horizon. In this paper, we consider the extension of the resource-constrained project scheduling problem with those partially renewable resources as well as generalized precedence constraints with the objective of minimizing the project duration (RCPSP/max- $$\pi $$ ). For this problem it is known that already the determination of a feasible solution is NP-hard in the strong sense. Hence, we present two different generation schemes that are able to find good feasible solutions in short time for most tested instances. The first one is a construction-based heuristic wherein the activities of the project are scheduled iteratively time- and resource-feasibly. The second one is a relaxation-based generation scheme, in which—starting from the schedule consisting of the earliest start times—resource conflicts are identified and resolved by inserting additional resource constraints.
Keywords
Funding Information
- Technische Universität Clausthal
This publication has 13 references indexed in Scilit:
- A branch-and-bound procedure for the resource-constrained project scheduling problem with partially renewable resources and general temporal constraintsOR Spectrum, 2020
- Partially Renewable Resources2014
- GRASP and path relinking for project scheduling under partially renewable resourcesEuropean Journal of Operational Research, 2008
- A scatter search algorithm for project scheduling under partially renewable resourcesJournal of Heuristics, 2006
- Project Scheduling with Time Windows and Scarce Resources2003
- Truncated branch-and-bound, schedule-construction, and schedule-improvement procedures for resource-constrained project schedulingOR Spectrum, 2001
- Project Scheduling Under Partially Renewable Resource ConstraintsManagement Science, 1999
- Distribution requirements and compactness constraints in school timetablingEuropean Journal of Operational Research, 1997
- An Efficient Integer Programming Algorithm with Network Cuts for Solving Resource-Constrained Scheduling ProblemsManagement Science, 1978
- Algorithm 97: Shortest pathCommunications of the ACM, 1962